SANJAC BESS
202.37 MW storage in Harris, TX · In queue since July 2021 · Proposed COD April 2027
202.37 MW
Capacity
1
Components
Battery
5y 4m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-04
Projected COD moved
4 times
Jan 2023 → Apr 2027
Net change
+51 months
first report to latest
Capacity
200 → 202 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Queue entry submitted to ERCOT, currently in Facility Study phase
ercotqueue.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0081/sanjac-bess
- ercotqueue.com/project/24INR0081
- ercotqueue.com/developer/castleman-power
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
Commercial operation date: Only LBNL queue snapshot provides a COD target of April 2027. No news coverage or press releases found discussing this specific project's timeline or construction status.
Developer: LBNL lists 'Castleman Power' as developer. No news coverage found to verify if this is a shell LLC or operating entity. Third-party queue trackers (ercotqueue.com, Cleanview) confirm same developer name with no additional parent company information.
Status: LBNL shows 'active' status in Facility Study phase. No news coverage found indicating construction start, financing close, or project withdrawal. Third-party trackers assign low build probability (5% per ercotqueue.com).
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The SANJAC BESS project is a proposed 202.37 MW battery storage project located in Harris County, Texas. The project, developed by Castleman Power, is interconnected within the Electric Reliability Council of Texas (ERCOT) region. It consists of a single 202.37 MW battery component.
The project entered the ERCOT interconnection queue as entry ERCOT-24INR0081 on July 8, 2021. Its proposed commercial operation date is April 4, 2027. The project's interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the 40270 Riverside 138kV.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Castleman Power
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
40270 Riverside 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Riverside Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.