Quarter Ranch Solar
154.12 MW generation in Zapata, TX · In queue since July 2021 · Proposed COD October 2028
154.12 MW
Capacity
1
Components
Solar
5y 4m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-15
Projected COD moved
3 times
Mar 2024 → Oct 2028
Net change
+55 months
first report to latest
Capacity
154 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Solar lease agreement signed with Gransolar Texas Three LLC for Quarter Ranch Solar facility
interchange.puc.texas.govResearch sources and reasoning (3 recorded sources)
low confidence at research time
- interchange.puc.texas.gov/Documents/55296_251_1358078.PDF
- gem.wiki/Quarter_Ranch_Solar
- interconnection.fyi/project/ercot-24inr0077
Commercial operation date: Only LBNL queue data provides a COD target of October 2028. No news sources or press releases mention project timeline, financing, or construction milestones to validate or contradict this date.
Developer: LBNL filing entity is 'Gransolar Texas Three LLC', a project-specific LLC. The PUC Interchange document from January 2024 confirms the solar lease agreement with this entity, indicating Gransolar is the parent operating company.
Status: LBNL status shows 'Active' in Facility Study phase. Global Energy Monitor (Feb 2026) confirms pre-construction status. No evidence of construction start, financing, or permitting milestones.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Quarter Ranch Solar is a proposed 154.12 MW solar generation project located in Zapata County, Texas. The project, developed by Gransolar Texas Three LLC, is in the ERCOT interconnection queue as entry ERCOT-24INR0077, with a queue entry date of July 13, 2021. The proposed commercial operation date is October 15, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project is planned to connect to the 80223 Cenizo Substation at 345kV. Quarter Ranch Solar has been mentioned in recent news coverage related to the energy industry.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Zapata
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Gransolar Texas Three LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
80223 Cenizo Substation 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Cenizo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.