Sypert Branch Solar Project (ERCOT-24INR0070) — Project Summary

Queue ID
ERCOT-24INR0070
Capacity
261.15 MW
Technology
Solar
Status
active
Location
Milam, TX
Region
ERCOT
Developer
Sypert Branch Solar LLC
IA Status
IA Executed

Sypert Branch Solar Project

ERCOT-24INR0070BetaActiveSolarERCOTLBNL + Live

261.15 MW generation in Milam, TX · In queue since September 2021 · Proposed COD April 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

261.15 MW

Capacity

1

Components

Solar

5y 2m

In Queue

IA Executed

IA Phase

Signed Oct 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 1m

IA → COD

2y 6m

Total Duration

2y 1m

Schedule

7 months past proposed COD

Construction75%
Queue EntrySep 21, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 12, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-04-30

Queue history
24INR0070 · 54 monthly ERCOT reports, Apr 2022 – Sep 2026

Projected COD moved

4 times

Dec 2024 → Apr 2026

Net change

+16 months

first report to latest

Capacity

262 → 261 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 21, 2021
Facilities study approvedOct 31, 2024
Interconnection agreement signedOct 12, 2023
Approved for energizationDec 10, 2025
Approved for synchronizationDec 12, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Dec 2025
Differs from queue: Apr 30, 2026
Developer in saved assessment
Engie North America
Filed as Sypert Branch Solar LLC
Status at research time
IA Executed
IA Executed — construction phase with Meta PPA secured, targeting late 2025 COD
Financing
Secured
260 MW Environmental Attributes Purchase Agreement (EAPA) with Meta announced October 2024, securing project revenue stream. ENGIE developing, constructing, and operating.

Milestones in this assessment

IA executedOct 12, 2023

Interconnection Agreement executed with ERCOT

utilitydive.com
Financing closeOct 2024

Meta signs 260 MW EAPA with ENGIE for all energy output from Sypert Branch

engie-na.com
COD targetDec 2025Latest in this assessment

Project expected to come online late 2025 per ENGIE and Meta announcement

utilitydive.com
Research sources and reasoning (5 recorded sources)

high confidence at research time

  1. utilitydive.com/news/engie-meta-solar-energy-data-center-purchase-agreement-power/731649/
  2. esgtoday.com/meta-signs-260-mw-solar-energy-purchase-deal-with-engie-to-support-net-zero-goals/
  3. engie-na.com/engie-and-meta-announce-260-mw-renewable-energy-agreement/
  4. datacenterdynamics.com/en/news/meta-signs-renewable-supply-agreement-with-engie-in-texas/
  5. solarbytes.info/engie-meta-completed-eapa-260-mw-sypert-branch-solar-project-texas/

Commercial operation date: Multiple independent sources from Oct-Nov 2024 (Utility Dive, ESG Today, Data Center Dynamics, ENGIE press release) consistently state the project will come online in 'late 2025', which contradicts LBNL's April 2026 target by approximately 4-6 months. The late-2025 timeline is tied to the Meta PPA announcement and represents the developer's current financing-backed target.

Developer: LBNL filing uses project-specific LLC 'Sypert Branch Solar LLC', while all press releases and news coverage (ENGIE corporate announcement, Utility Dive, ESG Today) identify ENGIE North America as the developer, owner, and operator. This is a standard shell-LLC vs. parent-company structure.

Status: LBNL status 'Active' with IA executed Oct 2023 is accurate. Project has advanced significantly with Meta PPA announcement in Oct 2024 and ENGIE confirming they will construct and operate the facility.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Sypert Branch Solar Project is a proposed solar generation project located in Milam County, Texas, with a total capacity of 261.15 MW. Developed by Sypert Branch Solar LLC, the project consists entirely of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-24INR0070, with a queue entry date of September 21, 2021, and a proposed commercial operation date of April 30, 2026.

The project's interconnection agreement has been executed as of October 12, 2023. The point of interconnection is Tap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2. The Sypert Branch Solar Project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Milam

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Sypert Branch Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2

Data Source

LBNL + Live

TransactionPPAEnergetica India Magazine · 2024-11-01
OfftakerMetaEnergetica India Magazine · 2024-11-01
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
HIGH
Nearest Node (Estimated)
SYBR_SLR_RN
POI Substation
Buckholts Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.