Sypert Branch Solar Project
Type
Entity Briefing
Entity
Sypert Branch Solar Project
Generated
2026-10-19T22:05:27.501Z

Briefing on Sypert Branch Solar Project

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
261 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2026-04-30
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Sypert Branch Solar Project is a 261 MW Solar project in Texas, currently active.

Sypert Branch Solar is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-04-30.

Queue ID
ERCOT-24INR0070
Location
Milam, Texas
Technology
Solar
Developer
Sypert Branch Solar
Market / region
ERCOT
Point of interconnection
Tap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2

What stands out

1

Sypert Branch Solar Project is a 261 MW Solar project in Texas with status active.

2

Sypert Branch Solar is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-04-30.

4

Latest linked story: “ENGIE and Meta Announce 260 MW RE Agreement to Support Net Zero Goals” (Energetica India Magazine, 2024-11-01).

Market and operating context

Queue date
2021-09-21
Proposed COD
2026-04-30
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Sypert Branch Solar Project — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0070
LocationMilam, Texas
TechnologySolar
DeveloperSypert Branch Solar
Market / regionERCOT
Point of interconnectionTap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2
Queue date2021-09-21
Proposed COD2026-04-30