Jaguar Solar (ERCOT-24INR0038) — Project Summary

Queue ID
ERCOT-24INR0038
Capacity
300.87 MW
Technology
Solar+Battery
Status
active
Location
Mclennan, TX
Region
ERCOT
Developer
PP Jaguar Solar LLC
IA Status
IA Executed

Jaguar Solar

ERCOT-24INR0038BetaActiveSolarBatteryERCOTLBNL + Live

300.87 MW hybrid in Mclennan, TX · In queue since March 2021 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

300.87 MW

Capacity

1

Components

Solar

5y 8m

In Queue

IA Executed

IA Phase

Signed Sep 2022

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 6m

IA → COD

5y 3m

Total Duration

1y 6m

Construction75%
Queue EntryMar 18, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementSep 12, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2027-12-11

Queue history
24INR0038 · 59 monthly ERCOT reports, Jul 2021 – Sep 2026

Projected COD moved

4 times

Apr 2024 → Dec 2027

Net change

+44 months

first report to latest

Capacity

300 → 301 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 18, 2021
Facilities study approvedAug 30, 2022
Interconnection agreement signedSep 12, 2022
On ERCOT's inactive listSep 2022 – Dec 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 2y 3m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneinstallation completedElectrek · 2024-08-26

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2028
Differs from queue: Dec 11, 2027
Developer in saved assessment
Perfect Power LLC (owned by FIC Partners Management LP)
Ownership change in saved research
Status at research time
Construction
LBNL shows Active with IA Executed (2022-09-12). The developer says construction began in 2025, and the co-located 300 MW Jaguar BESS reached COD in Sep and Dec 2025.
Financing
Not recorded
Ownership history
  1. —·Perfect Power LLC (via PP Jaguar Solar LLC)→FIC Partners Management LPrenewablesnow.com

Milestones in this assessment

Groundbreaking2025Latest in this assessment

Perfect Power says the 300 MWac Jaguar Solar began construction in 2025.

perfectpowerllc.com
Research sources and reasoning (6 recorded sources)

medium confidence at research time

  1. perfectpowerllc.com/proj/sum.html
  2. perfectpowerllc.com/proj/under_dev.html
  3. pv-tech.org/fic-acquires-us-solar-plus-storage-firm-perfect-power/
  4. renewablesnow.com/news/fic-acquires-owner-of-1-15-gw-jaguar-solar-bess-platform-in-texas-1298980/
  5. cleanview.co/power-projects/planned/solar-farms/texas/24INR0038/jaguar-solar
  6. infrasure.ai/project/ercot-24inr0038-jaguar-solar

Commercial operation date: The developer's site says Jaguar Solar "began construction in 2025 and is expected to be operational in 2028", about one year after the LBNL date of 2027-12-11. Cleanview's "Expected online 2027" appears to repeat the queue data, so it is not independent.

Developer: PP Jaguar Solar LLC is the project shell for Perfect Power, which develops and operates the co-located Jaguar BESS and Jaguar Solar. PV Tech and Renewables Now report that FIC Partners Management LP recently acquired Perfect Power. The news-extracted facts (Enbridge, Toyota PPA, True North/Avangrid) describe other projects and were disregarded.

Status: The developer's project pages state that Jaguar Solar began construction in 2025 and is targeting 2028 operation. The queue status is still Active, but ground reality is past the pure queue stage.

Project lifecycle
as of 2024-11-01
PhaseConstructionElectrek · 2024-11-01
OperationalNoElectrek · 2024-11-01
TechnologySolarElectrek · 2024-11-01
DeveloperEnbridgeElectrek · 2024-11-01
PPA offtakerAT&T, ToyotaElectrek · 2024-11-01
Permit decisionGrantedElectrek · 2024-11-01

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

PP Jaguar Solar is a proposed 300 MW solar generation project located in McLennan County, Texas. The project, developed by PP Jaguar Solar LLC, is interconnected within the ERCOT region under queue ID ERCOT-24INR0038. It entered the interconnection queue on March 18, 2021, and has a proposed commercial operation date of December 11, 2027. The project's Interconnection Agreement (IA) was executed on September 12, 2022.

The interconnection point of contact is Tap 345kV 13405 Tradinghouse SES - 68090 Sam Switch. The project has been featured in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Mclennan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

PP Jaguar Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 13405 Tradinghouse SES - 68090 Sam Switch

Data Source

LBNL + Live

DeveloperEnbridge±Electrek · 2024-11-01
TransactionPPAElectrek · 2024-11-01
Deal value$1.1BElectrek · 2024-11-01
OfftakerToyotaElectrek · 2024-11-01
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
HIGH
Nearest Node (Estimated)
JAG_SLR_RN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-04-19

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.