Stoneridge Solar (ERCOT-24INR0031) — Project Summary

Queue ID
ERCOT-24INR0031
Capacity
201.6 MW
Technology
Solar
Status
active
Location
Milam, TX
Region
ERCOT
Developer
Stoneridge Solar, LLC
IA Status
IA Executed

Stoneridge Solar

ERCOT-24INR0031BetaActiveSolarERCOTLBNL + Live

201.6 MW generation in Milam, TX · In queue since October 2021 · Proposed COD December 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

201.6 MW

Capacity

1

Components

Solar

5y 1m

In Queue

IA Executed

IA Phase

Signed May 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 7m

IA → COD

3y 7m

Total Duration

1y 7m

Construction75%
Queue EntryOct 8, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 15, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-31

Queue history
24INR0031 · 56 monthly ERCOT reports, Feb 2022 – Sep 2026

Projected COD moved

6 times

Dec 2023 → Dec 2026

Net change

+36 months

first report to latest

Capacity

200 → 202 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 8, 2021
Facilities study approvedMay 21, 2024
Interconnection agreement signedMay 15, 2023
Approved for energizationJan 10, 2025
Approved for synchronizationApr 1, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Nov 26, 2025
Differs from queue: Dec 31, 2026
Developer in saved assessment
RWE Clean Energy
Filed as Stoneridge Solar, LLC
Status at research time
Online
Online — commissioned November 26, 2025 with 200 MW solar + 100 MW/200 MWh battery storage
Financing
Secured
Financing secured (amount not publicly disclosed). Project successfully completed construction and commissioned by RWE Clean Energy in November 2025.

Milestones in this assessment

IA executedMay 15, 2023

Interconnection Agreement executed with ERCOT

rwe.com
COD targetNov 26, 2025Latest in this assessment

Project commissioned with 200 MW solar and 100 MW/200 MWh battery storage

rwe.com
Research sources and reasoning (5 recorded sources)

high confidence at research time

  1. rwe.com/en/press/rwe-clean-energy/2025-11-26-rwe-brings-more-american-generated-power-to-texax-with-stoneridge-project/
  2. solarpowerworldonline.com/2025/11/rwe-powers-on-200-mw-solar-storage-project-in-east-central-texas/
  3. energy-storage.news/rwe-commissions-texas-solar-plus-storage-project/
  4. pv-tech.org/rwe-commissions-200mw-100mw-200mwh-solar-plus-storage-project-texas/
  5. rwe.com/en/press/rwe-americas/2026-03-05-rwe-commissions-2-gw-of-new-energy-projects-in-the-us/

Commercial operation date: Multiple independent sources (RWE press release, Solar Power World, PV Tech, Energy-Storage.News) confirm the project was commissioned on November 26, 2025. LBNL's proposed COD of April 2026 was close but the project came online 5 months earlier than the queue filing indicated.

Developer: LBNL filing lists 'Stoneridge Solar, LLC' as the developer entity, which is a project-specific LLC. All press releases and news coverage identify RWE Clean Energy as the actual operating company that developed, owns, and commissioned the project.

Status: Project transitioned from 'Active' queue status to operational. Multiple sources confirm commissioning in late November 2025, with RWE's official press release stating the project is now delivering power to the Texas grid.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Stoneridge Solar is a proposed 201.6 MW solar generation project located in Milam County, Texas. The project, developed by Stoneridge Solar, LLC, is interconnected within the ERCOT region under queue ID ERCOT-24INR0031. It entered the queue on October 8, 2021, with a proposed commercial operation date of April 1, 2026. The project's Interconnection Agreement (IA) was executed on May 15, 2023.

The proposed project is linked to the existing operating plant named Stoneridge Solar, LLC (EIA plant ID 69027). Recent news coverage has highlighted the project, focusing on grid-related aspects.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Milam

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Stoneridge Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345 kV 13429 SANDOW SWITCH - 7040 AUSTROP Beulah Switch to tap above line

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
HIGH
Nearest Node (Estimated)
STRG_SLR_ALL

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-19

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.