Compadre Solar
405.7 MW generation in Hill, TX · In queue since March 2021 · Proposed COD October 2026
405.7 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Phase
Signed Nov 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 8m
IA → COD
3y 11m
Total Duration
1y 8m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2026-10-31
Projected COD moved
12 times
Oct 2024 → Oct 2026
Net change
+24 months
first report to latest
Capacity
405 → 406 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection agreement executed at the tap 345kV 68090 Sam Switch - 1907 Venus POI.
infrasure.aiResearch sources and reasoning (5 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-24inr0023-compadre-solar
- cleanview.co/power-projects/planned/solar-farms/texas/24INR0023/compadre-solar
- interconnection.fyi/project/ercot-24inr0023
- app.nrgmap.com/queues/ercot-24inr0023
- interconnection.fyi/project/ercot-23inr0296
Commercial operation date: No developer press release or financing-backed target was found. Aggregators that mirror queue data (Cleanview: 'Expected online 2026'; Infrasure: proposed COD between Feb and Apr 2026) are within a year of the LBNL date of 2026-10-31, so the LBNL date is kept.
Developer: Only the LBNL filing entity and aggregators that copy it (Infrasure: 'The developer is Hill Solar I, LLC') name a developer. No parent or operating company was identified. 'Compadre Solar, LLC' appears only as owner of the separate 150 MW Cooke County project (Trojan Solar SLF, 23INR0296), so it was not used.
Status: Interconnection.fyi and NRG Map list the project as active, which matches LBNL. Results showing 'operational', 'commissioned' or 'under construction' (Cleanview operating page, GEM, ercotqueue.com, interxdata) appear to conflate it with the 150 MW Compadre Solar / Trojan Solar SLF project in Cooke County (EIA plant 67765). They were discarded.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Compadre Solar is a proposed 406.14 MW solar generation project located in Hill County, Texas. The developer is Hill Solar I, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-24INR0023, with a queue entry date of March 16, 2021, and a proposed commercial operation date of February 27, 2026.
The interconnection agreement for Compadre Solar was executed on November 12, 2022. The point of interconnection is the tap 345kV 68090 Sam Switch - 1907 Venus. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hill
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hill Solar I, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 68090 Sam Switch - 1907 Venus
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.