Pinnington Storage
502.67 MW generation in Jack, TX · In queue since December 2020 · Proposed COD April 2029
502.67 MW
Capacity
1
Components
Battery
5y 11m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 4m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-20
Projected COD moved
4 times
Jun 2024 → Apr 2029
Net change
+58 months
first report to latest
Capacity
500 → 503 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-24inr0011-pinnington-storage
- cleanview.co/power-projects/planned/battery-storage-projects/texas/24INR0011/pinnington-storage
- repsol.com/en/press-room/press-releases/2026/repsol-achieves-commerical-operations-825-mw-pinnington-solar-facility-texas/index.cshtml
Commercial operation date: Only the LBNL/ERCOT filing gives a COD for this storage entry (2029-04-20). Infrasure and Cleanview repeat the same 2029 date, so they are not independent. The Repsol commercial-operation releases cover the separate 825 MW Pinnington Solar entry (24INR0010), not this battery entry (24INR0011).
Developer: The LBNL filing LLC carries the Hecate Energy name, and Infrasure notes Hecate announced plans for 7,000 acres on the Jack/Palo Pinto County line. No source says who owns the storage entry now. Repsol operates the companion solar plant, but nothing shows it took over the storage project.
Status: LBNL shows active with a Facility Study IA status and no IA date. Nothing in the search results shows the storage entry withdrawn, built, or under construction. The operating-status coverage applies to the separate solar queue entry.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Pinnington Storage project is a proposed 508.7 MW battery energy storage system in Jack County, Texas. The project, developed by Hecate Energy Longhorn Storage LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-24INR0011, with a queue entry date of December 3, 2020. Its proposed commercial operation date is April 20, 2029, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project involves a point of interconnection (POI) at the tap of both 345kV 1430 Graham - 1436 Parker 345kV lines. Recent news coverage indicates ongoing development activity related to the Pinnington Storage project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jack
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hecate Energy Longhorn Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap both 345kV 1430 Graham - 1436 Parker 345kV lines
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Obtain a complete list of Hecate Energy's operating assets, including in-service dates, to accurately identify plants added since 2023.
Structured data lookup for Hecate Energy with rankings and aggregations.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.