Nockenut Springs Solar 2 (ERCOT-24INR0007) — Project Summary

Queue ID
ERCOT-24INR0007
Capacity
203.26 MW
Technology
Solar
Status
active
Location
Guadalupe, TX
Region
ERCOT
Developer
Pecan Springs Energy, LLC
IA Status
IA Executed

Nockenut Springs Solar 2

ERCOT-24INR0007BetaActiveSolarERCOTLBNL + Live

203.26 MW generation in Guadalupe, TX · In queue since September 2020 · Proposed COD June 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

203.26 MW

Capacity

1

Components

Solar

6y 2m

In Queue

IA Executed

IA Phase

Signed Nov 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 2m

IA → COD

5y 7m

Total Duration

3y 2m

Construction75%
Queue EntrySep 25, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 17, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2029-06-05

Queue history
24INR0007 · 73 monthly ERCOT reports, Sep 2020 – Sep 2026

Projected COD moved

3 times

Dec 2024 → Jun 2029

Net change

+54 months

first report to latest

Capacity

203 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 25, 2020
Interconnection agreement signedNov 17, 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Jun 5, 2029
From queue filing
Developer in saved assessment
Pecan Springs Energy, LLC
From queue filing
Status at research time
IA Executed
IA Executed — interconnection agreement signed November 2023, project remains in active development with 2029 COD target
Financing
Not recorded

Milestones in this assessment

IA executedNov 17, 2023

Interconnection Agreement executed with ERCOT

ercot.com
COD targetJun 5, 2029Latest in this assessment

Target commercial operation date for 203.26 MW solar facility

ercot.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. ercot.com/files/docs/2026/05/01/MORA_July2026.pdf
  2. ercot.com/files/docs/2026/04/09/3.-EIR-CPS-Energy-Helotes-Reactive-Power-Planning-Project-Recommendation-RPG_April_2026_FINAL.pdf
  3. ercot.com/files/docs/2026/01/08/Capacity-Changes-by-Fuel-Type-Charts_December_2025.xlsx
  4. ercotqueue.com/project/24INR0007

Commercial operation date: LBNL queue snapshot shows proposed COD of 2029-06-05. Multiple ERCOT planning documents (MORA July 2026, CPS Energy reactive power study April 2026) confirm this same 2029 target. No contradictory news or press releases found.

Developer: All sources consistently identify developer as Pecan Springs Energy, LLC. No evidence of shell LLC structure or parent company differentiation. No ownership changes or acquisitions found in search results.

Status: LBNL shows IA executed on 2023-11-17 with active status. ERCOT planning documents from 2026 continue to list project as active with unchanged 2029 COD, indicating no withdrawal or suspension.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Nockenut Springs Solar 2 is a proposed solar generation project located in Guadalupe County, Texas, within the ERCOT region. The project, developed by Pecan Springs Energy, LLC, has a total capacity of 203.26 MW. It consists entirely of solar photovoltaic generation.

The project is listed in the ERCOT interconnection queue as entry ERCOT-24INR0007, with a queue entry date of September 25, 2020. The proposed commercial operation date is June 5, 2029. Its interconnection status is currently in the Facility Study phase.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Guadalupe

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Pecan Springs Energy, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV 5133 Elm Creek - 5915 STP ckt 1

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Elm Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.