Hidden Lakes BESS
9.9 MW storage in Galveston, TX · In queue since June 2023 · Proposed COD May 2026
9.9 MW
Capacity
1
Components
Battery
3y 1m
In Queue
IA Executed
IA Phase
Signed Feb 2024
Queue → IA
8 months
IA → COD
2y 3m
Total Duration
8 months
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-05-24
The Hidden Lakes BESS project is a proposed 9.9 MW battery storage project located in Galveston County, Texas. Developed by SBESS TX 6 LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-23INR0617. The project entered the queue on June 14, 2023, with a proposed commercial operation date of November 30, 2025. An Interconnection Agreement (IA) has been executed as of February 7, 2024.
The Hidden Lakes BESS project is linked to the existing Hidden Lakes operating plant (EIA ID 67844). The interconnection point is designated as HDNLAKES, PTI Bus# 38900, Load XFMR Name HDLAKE_2, at a transmission level voltage of 138 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Galveston
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
SBESS TX 6 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Station Name: HDNLAKES PTI Bus#: 38900 Load XFMR Name: HDLAKE_2 Transmission Level Voltage: 138 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HDNLAKES_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Hidden Lakes BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.