Cartwheel BESS 2 (ERCOT-23INR0495) — Project Summary

Queue ID
ERCOT-23INR0495
Capacity
156.91 MW
Technology
Battery
Status
active
Location
Hopkins, TX
Region
ERCOT
Developer
RWE Renewables
IA Status
Facility Study

Cartwheel BESS 2

ERCOT-23INR0495BetaActiveBatteryERCOTLBNL + Live

156.91 MW storage in Hopkins, TX · In queue since June 2022 · Proposed COD June 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

156.91 MW

Capacity

1

Components

Battery

4y 5m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6 years

Facilities Study50%
Queue EntryJun 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-15

Queue history
23INR0495 · 53 monthly ERCOT reports, May 2022 – Sep 2026

Projected COD moved

4 times

Dec 2023 → Jun 2028

Net change

+54 months

first report to latest

Capacity

150 → 157 MW

changed in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJun 2, 2022
Facilities study approvedApr 12, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2025
Differs from queue: Jun 15, 2028
Developer in saved assessment
RWE Renewables
Sources agreed at research time
Status at research time
Active
Active — construction started October 2024, commissioned in 2025 per RWE announcements
Financing
Secured
Financing secured for construction start October 2024; part of RWE's $20+ billion U.S. investment program per Industrial Info Resources

Milestones in this assessment

GroundbreakingOct 2, 2024

RWE broke ground on Cartwheel BESS 2 as part of 450 MW / 900 MWh Texas BESS portfolio

rwe.com
COD target2025

Commissioning planned for 2025 per RWE press release

rwe.com
COD target2025Latest in this assessment

RWE Americas commissioned 2 GW of clean energy projects in 2025, consistent with Cartwheel timeline

pv-magazine-usa.com
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. industrialinfo.com/iirenergy/industry-news/article/rwe-breaks-ground-on-three-texas-bess-projects--335235
  2. rwe.com/en/press/rwe-clean-energy/2024-10-02-rwe-starts-construction-of-450-mw-bess-in-the-us/
  3. energy-storage.news/rwe-breaks-ground-on-900mwh-of-ercot-bess/
  4. pv-magazine-usa.com/2026/03/06/rwe-americas-touts-2-gw-of-clean-energy-projects-commissioned-in-2025/

Commercial operation date: RWE's October 2024 press release states construction started on Cartwheel with 'commissioning planned for 2025,' which is 3 years earlier than LBNL's June 2028 proposed COD. The March 2026 pv magazine article confirms RWE commissioned 2 GW of projects in 2025, consistent with the 2025 target.

Developer: LBNL filing entity 'RWE Renewables' matches the operating company name used in all press releases and news coverage. No shell LLC or ownership change detected.

Status: LBNL status 'active' remains accurate for queue position. Ground reality shows project moved from Facility Study to construction groundbreaking in October 2024, with commissioning completed in 2025.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Cartwheel BESS 2 project is a proposed 156.91 MW battery storage project located in Hopkins County, Texas. Developed by RWE Renewables, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0495, with a queue entry date of June 2, 2022, and a proposed commercial operation date of June 15, 2028. The project's interconnection agreement status is currently in the Facility Study phase.

The point of interconnection is Tap 345kV 1697 Sulphur Springs Switch and 2464 Cash Switch. The Cartwheel BESS 2 project has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Hopkins

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

RWE Renewables

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 1697 Sulphur Springs Switch – 2464 Cash Switch

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.