Cartwheel BESS 1
154.2 MW storage in Hopkins, TX · In queue since June 2022 · Proposed COD December 2026
154.2 MW
Capacity
1
Components
Battery
4y 5m
In Queue
IA Executed
IA Phase
Signed Nov 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 5m
IA → COD
3y 1m
Total Duration
1y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2026-12-31
Projected COD moved
6 times
Dec 2023 → Dec 2026
Net change
+36 months
first report to latest
Capacity
150 → 154 MW
changed in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Generation Interconnection Agreement executed between Oncor and Cartwheel BESS, LLC
interchange.puc.texas.govRWE breaks ground on Cartwheel BESS 1 as part of 450 MW / 900 MWh Texas BESS portfolio
rwe.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- rwe.com/en/press/rwe-clean-energy/2024-10-02-rwe-starts-construction-of-450-mw-bess-in-the-us/
- energy-storage.news/rwe-breaks-ground-on-900mwh-of-ercot-bess/
- industrialinfo.com/iirenergy/industry-news/article/rwe-breaks-ground-on-three-texas-bess-projects--335235
- energy-storage.news/rwe-brings-online-four-bess-projects-in-13gw-us-clean-energy-portfolio/
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
Commercial operation date: RWE's October 2024 press release states 'commissioning planned for 2025' for Cartwheel BESS, aligning with LBNL's proposed COD of 2025-12-23. March 2026 article confirms RWE brought online four BESS projects, consistent with 2025-2026 timeline.
Developer: LBNL filing entity is 'Cartwheel BESS, LLC' (project SPV), but multiple October 2024 sources confirm RWE as the actual developer and owner breaking ground on the project.
Status: LBNL shows 'Active' with IA Executed (Nov 2023). RWE announced construction start October 2, 2024 across multiple press releases, upgrading status from Active to Construction.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Cartwheel BESS 1 is a proposed energy storage project located in Hopkins County, Texas, with a total capacity of 154.2 MW. The project, developed by Cartwheel BESS, LLC, consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0494, with a queue entry date of June 2, 2022, and a proposed commercial operation date of December 23, 2025.
The project has an Interconnection Agreement (IA) executed on November 10, 2023. The Point of Interconnection (POI) is Tap 345kV 1697 Sulphur Springs Switch _x0013_ 2464 Cash Switch.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hopkins
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cartwheel BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1697 Sulphur Springs Switch – 2464 Cash Switch
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- POI Substation
- Sulphur Springs Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.