Sepanta Solar (ERCOT-23INR0473) — Project Summary

Queue ID
ERCOT-23INR0473
Capacity
217.26 MW
Technology
Solar
Status
active
Location
Nolan, TX
Region
ERCOT
Developer
BREG - Belgian Renewable Energy Group
IA Status
Facility Study

Sepanta Solar

ERCOT-23INR0473BetaActiveSolarERCOTLBNL + Live

217.26 MW generation in Nolan, TX · In queue since October 2022 · Proposed COD September 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

217.26 MW

Capacity

1

Components

Solar

4y 1m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 11m

Facilities Study50%
Queue EntryOct 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-18

Queue history
23INR0473 · 47 monthly ERCOT reports, Nov 2022 – Sep 2026

Projected COD moved

5 times

Feb 2024 → Sep 2029

Net change

+67 months

first report to latest

Capacity

217 → 218 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 18, 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
—
Developer in saved assessment
BREG (Belgian Renewable Energy Group)
Sources agreed at research time
Status at research time
Active
Active — Under Development, interconnection studies in final stage per BREG, construction targeted Q1 2025
Financing
Not recorded

Milestones in this assessment

Groundbreakingundefined 2025

Construction start targeted for beginning of 2025 (Q1 2025 NTP)

breg.group
COD targetundefined 2027Latest in this assessment

BREG targets Q1 2027 commercial operations for 225 MW solar project

breg.group
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. breg.group/en-us/projects/sepanta-solar
  2. interconnection.fyi/project/ercot-23inr0473
  3. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-ad5
  4. images1.showcase.com/d2/-0De-RO-jQonkpQ2jP1NIhlV4X4KhA7CUOhUCTtJjTw/document.pdf

Commercial operation date: BREG's official project page states 'Target COD: Q1 2027' and 'Construction will start in the beginning of 2025', contradicting LBNL's 2029-09-18 date by ~2.5 years. The developer's own website is the most authoritative source for current project timeline.

Developer: LBNL filing entity matches the operating company name. BREG's website confirms they are the developer, founded by Johan Vos in 2020 after selling WindVision to Blackrock in 2018.

Status: LBNL shows 'active' in Facility Study phase. BREG's project page (accessed 2025) confirms project is 'Under Development' with interconnection studies 'in their final stage' and all environmental studies completed with positive outcomes.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Sepanta Solar project is a proposed solar generation facility with a total capacity of 217.26 MW. The project is located in Nolan County, Texas, and is being developed by BREG - Belgian Renewable Energy Group. It is currently in the ERCOT interconnection queue as project ERCOT-23INR0473, with an interconnection queue entry date of October 18, 2022. The proposed commercial operation date is September 18, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.

The point of interconnection (POI) is at the 1339 ESKOTA_9 138kV substation, adjacent to the Oncor Sweetwater Eskota Switch #1339. The project has appeared in recent news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Nolan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BREG - Belgian Renewable Energy Group

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

1339 ESKOTA_9 138kV (PSS/E BUS #1339, Station Name: ESKOTA_8, kV: 138 kV) Property is adjacent (West) to the Oncor Sweetwater Eskota Switch #1339. POI would simply be on the other side of the fence of the switch.

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.