Ophelia Solar (ERCOT-23INR0471) — Project Summary

Queue ID
ERCOT-23INR0471
Capacity
110.5 MW
Technology
Solar
Status
active
Location
Ector, TX
Region
ERCOT
Developer
Ophelia Solar
IA Status
Facility Study

Ophelia Solar

ERCOT-23INR0471BetaActiveSolarERCOTLBNL + Live

110.5 MW generation in Ector, TX · In queue since September 2022 · Proposed COD September 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

110.5 MW

Capacity

1

Components

Solar

4y 2m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6 years

Facilities Study50%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-19

Queue history
23INR0471 · 50 monthly ERCOT reports, Aug 2022 – Sep 2026

Projected COD moved

4 times

Dec 2024 → Sep 2028

Net change

+45 months

first report to latest

Capacity

111 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 2, 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Sep 2028
From queue filing
Developer in saved assessment
Ophelia Solar
Filed as Ophelia Solar, LLC
Status at research time
Active
Active — Facility Study phase, tax incentive agreement approved by Ector County ISD in 2022
Financing
Not recorded

Milestones in this assessment

Permit approvedApr 2022

Tax abatement application (Chapter 313) filed with Ector County ISD

assets.comptroller.texas.gov
Permit approvedJun 2022Latest in this assessment

Application amendment filed requesting minimum job creation requirement waiver

assets.comptroller.texas.gov
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. oaoa.com/local-news/education/ecisd/projects-could-more-than-double-tax-base/
  2. assets.comptroller.texas.gov/ch313/1816/1816-ector-ophelia-app.pdf
  3. comptroller.texas.gov/economy/development/prop-tax/ch313/agreement-docs-details.php?id=1816
  4. assets.comptroller.texas.gov/ch313/1816/1816-ector-ophelia-appamend1.pdf

Commercial operation date: LBNL queue snapshot shows proposed COD of 2028-09-19. No independent news sources provide alternative COD targets; third-party aggregators (Cleanview, ercotqueue.com) simply echo the LBNL date.

Developer: Texas Comptroller tax incentive filings identify 'Ophelia Solar, LLC' as the legal applicant entity. LBNL lists 'Ophelia Solar' without LLC suffix, suggesting the LLC is the project vehicle. No parent company identified in available sources.

Status: LBNL shows 'active' status in Facility Study phase. Texas Comptroller records confirm tax abatement application filed and processed in April-June 2022, indicating project remains in development.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Ophelia Solar is a proposed 110.5 MW solar generation project located in Ector County, Texas. The development project, sponsored by Ophelia Solar, entered the ERCOT interconnection queue as entry ERCOT-23INR0471 on September 2, 2022. Its proposed commercial operation date is September 19, 2028.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is tapping the 138 kV line from Moss Switch (Bus# 1019) to Shin Oak POD (Bus# 11128), with a 110 MW PUN load at the high side of the MPT. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Ector

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Ophelia Solar

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138 kV Raceway Switch #18663 - Shin Oak POD #11128

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.