Bronze Quinta Storage
103.51 MW storage in Hidalgo, TX · In queue since January 2022 · Proposed COD January 2028
103.51 MW
Capacity
1
Components
Battery
4y 10m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6 years
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
Projected COD moved
3 times
Dec 2023 → Jan 2028
Net change
+49 months
first report to latest
Capacity
104 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
No interconnection agreement executed as of current queue status
ercotqueue.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/23INR0456/bronze-quinta-storage
- cleanview.co/developer/key-capture-energy
- interconnection.fyi/project/ercot-23inr0456
- ercotqueue.com/developer/kce-tx-28-llc
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
Commercial operation date: LBNL queue filing shows 2028-01-01 COD. One Cleanview source mentions 'December 2027' but this appears to be a rounding/display variation of the same target. No press releases or financing announcements found to contradict the LBNL date.
Developer: LBNL filing entity is 'KCE TX 28, LLC' which is a project-specific shell. Multiple Cleanview sources explicitly list this project under 'Key Capture Energy's Projects and Development Pipeline,' confirming KCE as the parent operating company.
Status: LBNL shows 'active' status at Facility Study stage with no IA executed. All third-party sources (Cleanview, interconnection.fyi, ercotqueue.com) confirm active status with 'No IA' designation. No evidence of construction activity or withdrawal.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Bronze Quinta Storage project is a proposed 103.51 MW battery storage project located in Hidalgo County, Texas. The developer is KCE TX 28, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0456, with a queue entry date of January 13, 2022. The proposed commercial operation date is January 1, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the S_MCALLN 8371 (S. McAllen 138kV Substation). The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hidalgo
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
KCE TX 28, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
S_MCALLN 8371 (S. McAllen 138kV Substation)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.