Bessie Storage
210.8 MW storage in Starr, TX · In queue since February 2022 · Proposed COD September 2029
210.8 MW
Capacity
1
Components
Battery
4y 9m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 7m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-28
Projected COD moved
11 times
Dec 2023 → Sep 2029
Net change
+69 months
first report to latest
Capacity
0 → 211 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Expected online November 2028 per Cleanview tracking
cleanview.coResearch sources and reasoning (3 recorded sources)
medium confidence at research time
- cleanview.co/planned-battery-projects/TX/23INR0455/bessie-storage
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
- interconnection.fyi/project/ercot-23inr0455
Commercial operation date: Cleanview (Result 5) reports expected online date of November 2028, which is ~11 months earlier than LBNL's 2029-09-28. This is a minor variance typical of queue data lag.
Developer: LBNL lists 'Bessie Energy Storage, LLC' as developer (project-specific shell). Result 10 (ERCOT BESS buildout report, May 2024) identifies the operating parent as 'Deriva Energy Storage, LLC'.
Status: LBNL status is 'active' at Facility Study stage. No search results indicate construction start, financing close, or withdrawal. Project remains in early interconnection phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Bessie Storage is a proposed 210.8 MW battery storage project located in Starr County, Texas. The project, being developed by Bessie Energy Storage, LLC, is interconnected within the ERCOT region under queue ID ERCOT-23INR0455. It entered the interconnection queue on February 21, 2022, and has a proposed commercial operation date of December 1, 2028. The project's interconnection status is currently in the Facility Study phase.
The Bessie Storage project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Starr
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bessie Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Charly Egner Substation Tap 345kV 80355 Del Sol - 80368 LV4 Bridge
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Sol Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesBattery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Bessie Storage
Data-driven briefing on Bessie Storage — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.