Coneflower Storage Project
170.85 MW storage in Chambers, TX · In queue since December 2021 · Proposed COD February 2028
170.85 MW
Capacity
1
Components
Battery
4y 11m
In Queue
IA Executed
IA Phase
Signed Mar 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 3m
IA → COD
3y 11m
Total Duration
2y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2028-02-28
Projected COD moved
4 times
Jun 2024 → Feb 2028
Net change
+44 months
first report to latest
Capacity
170 → 171 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with ERCOT, CenterPoint amendments filed April 2024
interchange.puc.texas.govERCOT capacity planning documents list 170.85 MW battery project with 2027 target
ercot.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&ItemMatch=Equal&FilingParty=centerpoint&DocumentType=ALL&SortBy=FilingParty&SortOrder=Descending
- ercot.com/files/docs/2025/11/06/Capacity-Changes-by-Fuel-Type-Charts_October_2025_PlannedMonthly.xlsx
- lorenz-g.github.io/tesla-megapack-tracker/all-big-batteries.html
- eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_05
Commercial operation date: LBNL proposes 2027-06-11 COD. Multiple aggregator sites (Cleanview, EIA) echo 2027 or August/September 2027, but these appear derivative of the LBNL filing rather than independent developer announcements. No press releases or news coverage found to validate or update this target.
Developer: LBNL filing uses project-LLC 'Coneflower Storage Project LLC'. The Big Battery Tracker (Result 10) explicitly identifies the parent as 'Acciona Energy USA Global, LLC', consistent with Acciona Energía's active battery storage portfolio.
Status: LBNL reports IA executed 2024-03-25. Texas PUC filings (Result 6) confirm CenterPoint amendments for the project in April 2024. No construction or financing announcements found; status remains pre-construction planning.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Coneflower Storage Project is a proposed 178.92 MW battery storage project located in Chambers County, Texas. The project, developed by Coneflower Storage Project LLC, is currently in the ERCOT interconnection queue as entry ERCOT-23INR0425, with a queue entry date of December 20, 2021. The proposed commercial operation date is June 11, 2027.
The project's Interconnection Agreement (IA) has been executed as of March 25, 2024. The Point of Interconnection (POI) is the 40855 JORDON 138 kV substation. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Chambers
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Coneflower Storage Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
40855 JORDON 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- HIGH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Coneflower Storage Project LLC
Data-driven briefing on Coneflower Storage Project LLC — fleet, generation, financial, and news signals.
Coneflower Storage Project
Data-driven briefing on Coneflower Storage Project — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.