THUNDER ROAD ENERGY STORAGE
153.4 MW storage in Dallas, TX · In queue since October 2021 · Proposed COD May 2027
153.4 MW
Capacity
1
Components
Battery
5y 1m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-31
Projected COD moved
2 times
Oct 2023 → May 2027
Net change
+43 months
first report to latest
Capacity
153 MW
unchanged in the reports
Latest stage
Cancelled
last listed Apr 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Queue entry date in ERCOT, Facility Study phase as of May 2024
modo-content-service-prod.s3.amazonaws.comResearch sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/23INR0391/thunder-road-energy-storage
- modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
- renewablesinfo.org/browse/projects/texas
- interconnection.fyi/projects/state/TX
Commercial operation date: LBNL queue snapshot shows proposed COD of 2027-05-31. No news articles or press releases found discussing this specific project's timeline, so LBNL remains the only source.
Developer: LBNL filing entity 'Hecate Grid Thunder Road Storage LLC' is a project-specific LLC. Parent operating company is Hecate Grid, a known battery storage developer.
Status: LBNL shows 'active' status with 'Facility Study' IA status. No news coverage found indicating construction start, financing close, or status changes.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Thunder Road Energy Storage is a proposed 153.4 MW battery storage project located in Dallas County, Texas. The project, developed by Hecate Grid Thunder Road Storage LLC, is currently in the ERCOT interconnection queue as entry ERCOT-23INR0391, with a queue entry date of October 22, 2021. Its proposed commercial operation date is May 31, 2027, and its interconnection status is currently in the Facility Study phase.
The Thunder Road Energy Storage project has been the subject of recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Apr 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Dallas
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hecate Grid Thunder Road Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
12491 FISH CREEK 138KV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Fish Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.