Briefing/projectactive
THUNDER ROAD ENERGY STORAGE is a 153 MW Battery project in Texas, currently active.
Hecate Grid Thunder Road Storage LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-05-31.
- Queue ID
- ERCOT-23INR0391
- Location
- Dallas, Texas
- Technology
- Battery
- Developer
- Hecate Grid Thunder Road Storage LLC
- Market / region
- ERCOT
- Point of interconnection
- 12491 FISH CREEK 138KV
What stands out
1
THUNDER ROAD ENERGY STORAGE is a 153 MW Battery project in Texas with status active.
2
Hecate Grid Thunder Road Storage LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2027-05-31.
Market and operating context
- Queue date
- 2021-10-22
- Proposed COD
- 2027-05-31
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.