Camp Creek Solar SLF (ERCOT-23INR0385) — Project Summary

Queue ID
ERCOT-23INR0385
Capacity
110 MW
Technology
Solar+Battery
Status
active
Location
Robertson, TX
Region
ERCOT
Developer
White Rock Solar, LLC
IA Status
IA Executed

Camp Creek Solar SLF

ERCOT-23INR0385BetaActiveSolarBatteryERCOTLBNL

110 MW hybrid in Robertson, TX · In queue since December 2021 · Proposed COD September 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

110 MW

Capacity

1

Components

Solar

4y 11m

In Queue

IA Executed

IA Phase

Signed Jul 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 7m

IA → COD

5y 2m

Total Duration

1y 7m

Construction75%
Queue EntryDec 24, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJul 15, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-09-15

Queue history
23INR0385 · 51 monthly ERCOT reports, Dec 2021 – Feb 2026

Projected COD moved

3 times

Nov 2023 → Sep 2028

Net change

+58 months

first report to latest

Capacity

166 → 110 MW

changed in the reports

Latest stage

Cancelled

last listed Feb 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 24, 2021
Facilities study approvedJan 26, 2024
Interconnection agreement signedJul 15, 2023
CancelledMar 30, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 4 years ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneentering permitting process · 2022-11NorthEscambia.com · 2022-11-28

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2026
Differs from queue: Sep 15, 2028
Developer in saved assessment
White Rock Solar, LLC
From queue filing
Status at research time
Active
Active — IA executed July 2023, but interconnection.fyi shows project as 'withdrawn' as of their latest update, creating status ambiguity
Financing
Not recorded

Milestones in this assessment

IA executedJul 15, 2023

ERCOT Standard Generation Interconnection Agreement executed with CenterPoint Energy Houston Electric

interchange.puc.texas.gov
COD target2026

ERCOT capacity chart lists 2026 as expected online date for 165.6 MW solar facility

ercot.com
COD targetJun 2028Latest in this assessment

Proposed completion date changed from December 2026 to June 2028 per April 2025 project update

interconnectionfyi.substack.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
  2. interconnection.fyi/project/ercot-23inr0385
  3. ercot.com/files/docs/2024/12/06/Capacity%20Changes%20by%20Fuel%20Type%20Charts_November_2024.xlsx
  4. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-ad5
  5. eta-publications.lbl.gov/sites/default/files/2024-09/hybrid_plant_tracking_2024_data_workbook.xlsx

Commercial operation date: LBNL shows 2028-09-15, but ERCOT's December 2024 capacity chart lists 2026 as the expected COD. Interconnection.fyi April 2025 update notes proposed completion changed from Dec 2026 to June 2028, suggesting ongoing delays but more recent target than LBNL's original filing.

Developer: All sources consistently identify White Rock Solar, LLC as the developer. No evidence of shell-LLC structure or ownership changes; appears to be the actual operating entity.

Status: LBNL shows 'active' with IA executed 2023-07-15. However, interconnection.fyi (Result 2) states project is 'currently withdrawn'. This discrepancy suggests recent status change not yet reflected in LBNL data, but ERCOT capacity charts through Nov 2024 still list the project, indicating it may remain in queue.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Camp Creek Solar SLF project is a proposed 165.6 MW solar generation project located in Robertson County, Texas. Developed by White Rock Solar, LLC, the project is currently in the ERCOT interconnection queue as entry ERCOT-23INR0385, with a queue entry date of December 24, 2021. The proposed commercial operation date is September 15, 2028. The project's Interconnection Agreement (IA) has been executed as of July 15, 2023.

The Camp Creek Solar SLF project has been featured in recent news coverage. The point of interconnection is at the TAP 345 KV 3400 TWIN OAK SWITCH - 46020 LIMESTONE PLANT CIRCUIT 1.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Feb 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Robertson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

White Rock Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

TAP 345 KV 3400 TWIN OAK SWITCH - 46020 LIMESTONE PLANT CIRCUIT 1

Data Source

LBNL

DeveloperFlorida Power & LightNorthEscambia.com · 2022-11-28
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.