Camp Creek Solar SLF
110 MW hybrid in Robertson, TX · In queue since December 2021 · Proposed COD September 2028
110 MW
Capacity
1
Components
Solar
4y 7m
In Queue
IA Executed
IA Phase
Signed Jul 2023
Queue → IA
1y 7m
IA → COD
5y 2m
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2028-09-15
ERCOT Standard Generation Interconnection Agreement executed with CenterPoint Energy Houston Electric
sourceERCOT capacity chart lists 2026 as expected online date for 165.6 MW solar facility
sourceProposed completion date changed from December 2026 to June 2028 per April 2025 project update
sourceThe Camp Creek Solar SLF project is a proposed 165.6 MW solar generation project located in Robertson County, Texas. Developed by White Rock Solar, LLC, the project is currently in the ERCOT interconnection queue as entry ERCOT-23INR0385, with a queue entry date of December 24, 2021. The proposed commercial operation date is September 15, 2028. The project's Interconnection Agreement (IA) has been executed as of July 15, 2023.
The Camp Creek Solar SLF project has been featured in recent news coverage. The point of interconnection is at the TAP 345 KV 3400 TWIN OAK SWITCH - 46020 LIMESTONE PLANT CIRCUIT 1.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Robertson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
White Rock Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345 KV 3400 TWIN OAK SWITCH - 46020 LIMESTONE PLANT CIRCUIT 1
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Camp Creek Solar SLFForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.