Camp Creek Solar SLF is a 110 MW Solar+Battery project in Texas, currently active.
White Rock Solar, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-09-15.
- Queue ID
- ERCOT-23INR0385
- Location
- Robertson, Texas
- Technology
- Solar+Battery
- Developer
- White Rock Solar, LLC
- Market / region
- ERCOT
- Point of interconnection
- TAP 345 KV 3400 TWIN OAK SWITCH - 46020 LIMESTONE PLANT CIRCUIT 1
What stands out
Camp Creek Solar SLF is a 110 MW Solar+Battery project in Texas with status active.
White Rock Solar, LLC is the reported developer.
The reported queue phase is IA Executed; proposed COD is 2028-09-15.
Latest linked story: “Fourth North Escambia FPL Solar Farm Planned South Of Bratt Road” (NorthEscambia.com, 2022-11-28).
Market and operating context
- Queue date
- 2021-12-24
- Proposed COD
- 2028-09-15
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.