Brizo BESS
140.76 MW storage in Victoria, TX · In queue since October 2021 · Proposed COD September 2027
140.76 MW
Capacity
1
Components
Battery
5y 1m
In Queue
IA Executed
IA Phase
Signed Mar 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 5m
IA → COD
2y 6m
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2027-09-01
Projected COD moved
3 times
May 2023 → Sep 2027
Net change
+52 months
first report to latest
Capacity
144 → 144 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Expected commercial operation date September 2027
cleanview.coResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/23INR0342/brizo-bess
- interconnection.fyi/project/ercot-23inr0342
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-db7
- ercot.com/files/docs/2025/12/04/Capacity-Changes-by-Fuel-Type-Charts_November_2025.xlsx
Commercial operation date: LBNL proposed COD of September 2027 is consistently reflected across all aggregator sources (Cleanview, interconnection.fyi, ERCOT capacity charts). No contradictory signals found in research.
Developer: All sources cite 'BRP Brizo BESS LLC' as the developer. No parent company or operating entity identified in search results. The LLC name appears to be the actual developer rather than a shell entity.
Status: LBNL reports IA executed on March 27, 2025, confirmed by interconnection.fyi newsletter (April 2025) noting 'IA date added March 26, 2025'. ERCOT capacity charts (November 2025) show project as not yet online.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Brizo BESS is a proposed 140.76 MW battery storage project located in Victoria County, Texas. The project, developed by BRP Brizo BESS LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0342, with a queue entry date of October 5, 2021. The proposed commercial operation date is December 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 138 kV Loop 463 Substation (#5680). The development has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Victoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Brizo BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Loop 463 Substation (#5680)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BRP_LOOP_RN
- POI Substation
- Loop 463 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.