Briefing/projectactive
Brizo BESS is a 141 MW Battery project in Texas, currently active.
BRP Brizo BESS LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-09-01.
- Queue ID
- ERCOT-23INR0342
- Location
- Victoria, Texas
- Technology
- Battery
- Developer
- BRP Brizo BESS LLC
- Market / region
- ERCOT
- Point of interconnection
- 138 kV Loop 463 Substation (#5680)
What stands out
1
Brizo BESS is a 141 MW Battery project in Texas with status active.
2
BRP Brizo BESS LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-09-01.
Market and operating context
- Queue date
- 2021-10-05
- Proposed COD
- 2027-09-01
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.