Tucana BESS
201.3 MW storage in Andrews, TX · In queue since June 2021 · Proposed COD March 2028
201.3 MW
Capacity
1
Components
Battery
4y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The Tucana BESS project is a proposed 201.3 MW battery storage project located in Andrews County, Texas. Developed by BRP Tucana BESS LLC, the project consists of a single 201.3 MW battery component.
The project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0278, with a queue entry date of June 3, 2021. The proposed commercial operation date is March 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the 1157 Andrews County South 138kV.
Generated from interconnection queue and public data sources
State
TX
County
Andrews
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Tucana BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1157 Andrews County South 138kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Andrews County South Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Tucana BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.