Briefing on Tucana BESS

Entity Briefing
Generated Sep 18, 2026·Dataset freshness not reported
201 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-03-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Tucana BESS is a 201 MW Battery project in Texas, currently active.

BRP Tucana BESS LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-03-01.

Queue ID
ERCOT-23INR0278
Location
Andrews, Texas
Technology
Battery
Developer
BRP Tucana BESS LLC
Market / region
ERCOT
Point of interconnection
1157 Andrews County South 138kV

What stands out

1

Tucana BESS is a 201 MW Battery project in Texas with status active.

2

BRP Tucana BESS LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-03-01.

Market and operating context

Queue date
2021-06-03
Proposed COD
2028-03-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Tucana BESS — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0278
LocationAndrews, Texas
TechnologyBattery
DeveloperBRP Tucana BESS LLC
Market / regionERCOT
Point of interconnection1157 Andrews County South 138kV
Queue date2021-06-03
Proposed COD2028-03-01