BRP Nile BESS (ERCOT-23INR0275) — Project Summary

Queue ID
ERCOT-23INR0275
Capacity
202.34 MW
Technology
Battery
Status
active
Location
Webb, TX
Region
ERCOT
Developer
BRP Nile BESS LLC
IA Status
Facility Study

BRP Nile BESS

ERCOT-23INR0275BetaActiveBatteryERCOTLBNL

202.34 MW storage in Webb, TX · In queue since May 2021 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

202.34 MW

Capacity

1

Components

Battery

5y 6m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 7m

Facilities Study50%
Queue EntryMay 31, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Queue history
23INR0275 · 58 monthly ERCOT reports, Jun 2021 – Mar 2026

Projected COD moved

2 times

Aug 2023 → Dec 2027

Net change

+52 months

first report to latest

Capacity

202 MW

unchanged in the reports

Latest stage

Cancelled

last listed Mar 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 31, 2021
CancelledApr 8, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 1, 2027
From queue filing
Developer in saved assessment
BRP Nile BESS LLC
From queue filing
Status at research time
Withdrawn
Withdrawn — interconnection.fyi lists project status as 'Withdrawn' as of their latest data, contradicting LBNL's 'Active' designation
Financing
Not recorded

Milestones in this assessment

Withdrawn

Project status changed to Withdrawn per interconnection.fyi queue tracking

interconnection.fyi
COD targetNov 2027Latest in this assessment

Proposed completion changed from November 2024 to November 2027

interconnectionfyi.substack.com
Research sources and reasoning (3 recorded sources)

medium confidence at research time

  1. interconnection.fyi/projects/state/TX/webb-county
  2. interconnectionfyi.substack.com/p/interconnectionfyi-weekly-digest
  3. renewablesinfo.org/project/ercot-23inr0275-brp-nile-bess

Commercial operation date: LBNL proposes December 2027 COD. One source mentions a COD change from Nov 2024 to Nov 2027, roughly aligning with LBNL. No independent recent press releases or financing announcements provide an alternative target date.

Developer: All sources consistently identify 'BRP Nile BESS LLC' as the developer. No parent company, operating entity, or ownership change information found in search results. The LLC appears to be the actual developer rather than a shell entity for a larger firm.

Status: LBNL snapshot shows 'active' status, but Result 5 from interconnection.fyi explicitly lists 'BRP Nile BESS, 23INR0275, Battery, Withdrawn' in their Webb County queue tracking. This is a more current ground-truth signal than the LBNL filing.

About

Saved background

Generated Apr 10, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The BRP Nile BESS project is a proposed 202.34 MW battery storage project located in Webb County, Texas. The developer is BRP Nile BESS LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-23INR0275, with a queue entry date of May 31, 2021.

The project's proposed commercial operation date is December 1, 2027. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the 80220 Cenizo 345kV substation. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Mar 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Webb

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BRP Nile BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

80220 Cenizo 345kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Cenizo Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.