Dodd Solar I (ERCOT-23INR0261) — Project Summary

Queue ID
ERCOT-23INR0261
Capacity
201.8 MW
Technology
Solar
Status
suspended
Location
Henderson, TX
Region
ERCOT
Developer
Forest Grove Solar LLC
IA Status
IA Executed

Dodd Solar I

ERCOT-23INR0261BetaSuspendedSolarERCOTLBNL + Live

201.8 MW generation in Henderson, TX · In queue since June 2021 · Proposed COD June 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

201.8 MW

Capacity

1

Components

Solar

5y 5m

In Queue

IA Executed

IA Phase

Signed Feb 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 8m

IA → COD

3y 4m

Total Duration

3y 8m

Suspended75%
Queue EntryJun 24, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 8, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-06-05

Queue history
23INR0261 · 48 monthly ERCOT reports, Apr 2022 – Mar 2026

Projected COD moved

4 times

May 2023 → Jun 2028

Net change

+61 months

first report to latest

Capacity

203 → 202 MW

changed in the reports

Latest stage

IA signed

last listed Mar 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJun 24, 2021
Facilities study approvedMar 13, 2024
Interconnection agreement signedFeb 8, 2025
On ERCOT's inactive listApr 2026 – Sep 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 6y 1m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneconstruction announcement · 2020-09-29KLTV.com · 2020-10-22
Expected COD2022KLTV.com · 2020-10-22

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2028
From queue filing
Developer in saved assessment
Vistra
Filed as Forest Grove Solar LLC
Status at research time
Suspended
Suspended — LBNL shows 'Active' with IA executed Feb 2025, but interconnection.fyi tracker explicitly lists status as 'Suspended' as of recent data
Financing
Not recorded

Milestones in this assessment

construction startSep 29, 2020

Construction announcement by Vistra for East Texas solar farm

kltv.com
IA executedFeb 8, 2025

ERCOT Standard Generation Interconnection Agreement executed

interchange.puc.texas.gov
COD targetSep 2027Latest in this assessment

Proposed completion changed from Feb 2026 to Sep 2027 (later updated to Jun 2028)

interconnectionfyi.substack.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. kltv.com/2020/10/22/two-solar-farms-set-be-constructed-east-texas/
  2. cleanview.co/power-projects/developers/vistra
  3. interconnectionfyi.substack.com/p/interconnectionfyi-weekly-digest
  4. interconnection.fyi/project/ercot-23inr0261
  5. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending

Commercial operation date: LBNL shows 2028-06-05 COD. News from 2020 expected 2022 COD, but that's now 6 years stale. Interconnection.fyi (Dec 2024) notes proposed completion changed from Feb 2026 to Sep 2027, suggesting continued delays. LBNL's 2028 date appears most current, though project has experienced significant slippage from original 2022 target.

Developer: LBNL filing entity is 'Forest Grove Solar LLC' (project shell). News from 2020 and Cleanview tracker both identify Vistra as the operating developer/owner. No evidence of ownership change since 2020.

Status: LBNL queue shows 'active' with IA executed 2025-02-08, but interconnection.fyi's Texas queue tracker explicitly lists project status as 'Suspended'. This discrepancy suggests recent status change not yet reflected in LBNL snapshot.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Dodd Solar I is a proposed 201.8 MW solar generation project in Henderson County, Texas, developed by Forest Grove Solar LLC. The project is listed in the Electric Reliability Council of Texas (ERCOT) interconnection queue under queue ID ERCOT-23INR0261 and consists of a single solar component. It is proposed to connect to the grid via a tap on the 138 kV line between the Eustace Southeast Switch (6951) and the Forest Grove Switch (3131).

The project entered the ERCOT queue on June 24, 2021, and executed an interconnection agreement on February 8, 2025. Its proposed commercial operation date is June 5, 2028, though its current queue status is listed as suspended. The project has been linked to an existing operating plant in U.S. Energy Information Administration (EIA) records, Forest Grove - Dodd (EIA plant ID 64131), with a match confidence of 0.77. Dodd Solar I has also appeared in recent news coverage, including three articles, two focused on project development and one on broader industry topics.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Mar 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Henderson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Forest Grove Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 6951 Eustace Southeast Switch – 3131 Forest Grove Switch

Data Source

LBNL + Live

DeveloperVistraKLTV.com · 2020-10-22
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Forest Grove Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.