Earthwise Solar
370.5 MW generation in Hardeman, TX · In queue since March 2022 · Proposed COD December 2028
370.5 MW
Capacity
1
Components
Solar
4y 8m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
Projected COD moved
2 times
Dec 2024 → Dec 2028
Net change
+48 months
first report to latest
Capacity
311 → 371 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- app.nrgmap.com/queues/ercot-23inr0233
- ercotqueue.com/project/23INR0233
- infrasure.ai/project/ercot-23inr0233-earthwise-solar
Commercial operation date: Every source that gives a COD (infrasure.ai, cleanview.co, NRG Map) repeats the LBNL/ERCOT proposed date of 2028-12-31. NRG Map lists 'Proposed online 2028-12-31'. No developer press release or news item gives an independent, financing-backed date.
Developer: All sources (ERCOT-derived trackers, NRG Map, ercotqueue.com) name only 'Quanah Solar 2', which looks like a project LLC. No source identifies a parent or operating company, so the filing name is used as-is.
Status: NRG Map, using ERCOT's status report dated 2026-09-01, shows the project active at the facility-study stage with no IA, which matches LBNL. interxdata.com's 'operational' label contradicts every other source and the missing IA, so it is disregarded.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Earthwise Solar is a proposed 370.5 MW solar generation project located in Hardeman County, Texas. The project, developed by Quanah Solar 2, is in the ERCOT interconnection queue as entry ERCOT-23INR0233, with a queue entry date of March 14, 2022. The proposed commercial operation date is December 31, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 60504 Tesla - 61001 Jim Treece. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hardeman
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Quanah Solar 2
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 60504 Tesla - 61001 Jim Treece
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MISAE_GEN_RN
- POI Substation
- Tesla Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.