El Patrimonio Solar
152.32 MW generation in Bexar, TX · In queue since March 2021 · Proposed COD April 2027
152.32 MW
Capacity
1
Components
Solar
5y 8m
In Queue
IA Executed
IA Phase
Signed Dec 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 9m
IA → COD
3y 4m
Total Duration
2y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2027-04-29
Projected COD moved
3 times
May 2024 → Apr 2027
Net change
+35 months
first report to latest
Capacity
100 → 152 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Groundbreaking ceremony held with CPS Energy and Ashtrom partners
newsroom.cpsenergy.comCommercial operation targeted for 2027 per financing announcement
jpost.comResearch sources and reasoning (7 recorded sources)
high confidence at research time
- newsroom.cpsenergy.com/el-patrimonio-solar-project-groundbreaking-2026/
- jpost.com/business-and-innovation/banking-and-finance/article-889723
- power-technology.com/news/ashtrom-secures-financing-texas-solar/
- renewablesnow.com/news/ashtrom-closes-usd-200m-in-bank-financing-for-texas-solar-project-1291278/
- constructionreviewonline.com/ground-broken-on-el-patrimonio-solar-project-in-bexar-county-texas/
- ashtromrenewableenergy.co.il/en/projects/el-patrimonio-solar-facility
- expressnews.com/business/real-estate/article/san-antonio-solar-farm-17856333.php
Commercial operation date: LBNL proposed COD of 2027-04-29 aligns with multiple 2026 sources stating 'commercial operation in 2027' (Jerusalem Post, Ashtrom corporate site). Financing closed March 2026 supports this timeline.
Developer: LBNL filing entity 'Heritage Solar, LLC' is a project SPV. All 2026 sources (CPS Energy newsroom, Power Technology, Jerusalem Post, Renewables Now) identify Ashtrom Renewable Energy as the developer and owner who secured financing and broke ground.
Status: LBNL shows 'Active' with IA executed Dec 2023. Multiple March 2026 sources confirm groundbreaking ceremony occurred and construction has begun (CPS Energy newsroom, Construction Review, Solarbytes).
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The El Patrimonio Solar project is a proposed 152.32 MW solar generation project located in Bexar County, Texas. The developer is Heritage Solar LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0207, with a queue entry date of March 16, 2021, and a proposed commercial operation date of April 29, 2027.
The project's Interconnection Agreement (IA) has been executed as of December 11, 2023. The point of interconnection (POI) is tap 138kV 5429 Trumbo - 5260 Leon Creek. The El Patrimonio Solar project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bexar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Heritage Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 5429 Trumbo - 5260 Leon Creek
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Trumbo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26