PEREGRINE BESS
150 MW generation in Goliad, TX · In queue since February 2021 · Proposed COD July 2027
Withdrawn from the ERCOT queue in September 2026, according to ERCOT's queue (Oct 2026).
150 MW
Capacity
1
Components
Battery
5y 9m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Proposed COD: 2027-07-01
Project withdrew from interconnection queue
Projected COD moved
1 time
May 2025 → Jul 2027
Net change
+26 months
first report to latest
Capacity
150 MW
unchanged in the reports
Latest stage
Cancelled
last listed Aug 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
FERC MBR filing shows Peregrine BESS 1 registration date of November 1, 2023
mbrweb.ferc.govResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/25INR0078/peregrine-bess-2
- 923theranch.com/post/harper-injunctions-filed-against-peregrine-bess-construction
- mbrweb.ferc.gov/SearchlkpEIA/Index?page=757
- gridinfo.com/consolidated-edison-development-inc
- renewablesinfo.org/project/ercot-25inr0078-peregrine-bess-2
Commercial operation date: LBNL proposed COD of July 2027 is corroborated by Cleanview aggregator data showing expected online date of July 2027. No contradictory recent sources found.
Developer: LBNL filing uses 'CED Development Inc.' but FERC MBR database and GridInfo clearly identify the parent as 'Consolidated Edison Development Inc.' operating multiple projects under CED entity.
Status: LBNL status is Active at Facility Study stage. September 2025 news shows community opposition with injunction filings, but no withdrawal or suspension announced. Project appears to be proceeding despite local resistance.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed PEREGRINE BESS project is a 150 MW battery storage development in Goliad County, Texas. Developed by CED Development Inc., the project is interconnected within the ERCOT region under queue ID ERCOT-23INR0206. The project entered the interconnection queue on February 10, 2021, and has a proposed commercial operation date of July 1, 2027. Its interconnection agreement status is currently in the Facility Study phase.
The project consists of 150 MW of battery storage capacity. It is proposed to connect to the ERCOT grid at the tap 345kV 8624 Grissom - 8164 Coleto Creek. The PEREGRINE BESS project has appeared in recent news coverage regarding energy storage developments in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Aug 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Goliad
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CED Development Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 8624 Grissom - 8164 Coleto Creek
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PERE_SLR_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-19