GALVANIC BESS (ERCOT-23INR0204) — Project Summary

Queue ID
ERCOT-23INR0204
Capacity
100 MW
Technology
Battery
Status
withdrawn
Location
Kinney, TX
Region
ERCOT
Developer
CED Development Inc
IA Status
Facility Study

GALVANIC BESS

ERCOT-23INR0204BetaWithdrawnBatteryERCOTLBNL + Live

100 MW storage in Kinney, TX · In queue since February 2021 · Proposed COD December 2027

Withdrawn from the ERCOT queue in September 2026, according to ERCOT's queue (Oct 2026).

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

100 MW

Capacity

1

Components

Battery

5y 9m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 10m

Queue EntryFeb 9, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Commercial Operation

Proposed COD: 2027-12-30

WithdrawnWithdrawn

Project withdrew from interconnection queue

Queue history
23INR0204 · 52 monthly ERCOT reports, May 2022 – Aug 2026

Projected COD moved

3 times

May 2024 → Dec 2027

Net change

+43 months

first report to latest

Capacity

100 MW

unchanged in the reports

Latest stage

Cancelled

last listed Aug 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 9, 2021
CancelledSep 14, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Dec 29, 2026
Differs from queue: Dec 30, 2027
Developer in saved assessment
CED Development Inc
Sources agreed at research time
Status at research time
Active
Active — Facility Study stage, no construction timeline announced
Financing
Not recorded

Milestones in this assessment

COD targetDec 29, 2026Latest in this assessment

Proposed completion date updated from Nov 2025 to Dec 29, 2026 per ERCOT interconnection study revision

interconnectionfyi.substack.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-7d3
  2. cleanview.co/power-projects/planned/battery-storage-projects/texas/23INR0204/galvanic-bess
  3. infrasure.ai/project/ercot-23inr0204-galvanic-bess
  4. ercotqueue.com/project/23INR0204

Commercial operation date: Interconnection FYI (Jan 2025) reports proposed completion changed from Nov 2025 to Dec 29, 2026, which is 1 year earlier than LBNL's Dec 2027 date. This reflects a more recent interconnection study update.

Developer: All sources consistently identify CED Development Inc as the developer with no evidence of shell LLC structure or ownership changes. LBNL filing entity matches operational company name.

Status: LBNL status 'Active' confirmed across all aggregator sources. Project remains in Facility Study phase with no public announcements of financing, permitting, or construction milestones.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Galvanic BESS project is a proposed 100 MW battery storage project located in Kinney County, Texas. Developed by CED Development Inc., the project is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-23INR0204 on February 9, 2021. The proposed commercial operation date is December 30, 2027, and its current interconnection status is Facility Study.

The Galvanic BESS project has been mentioned in recent news coverage related to the grid and energy industry.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Aug 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Kinney

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

CED Development Inc

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

8252 Bracketville 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.