Elbus BESS
200.99 MW storage in Caldwell, TX · In queue since December 2020 · Proposed COD June 2028
200.99 MW
Capacity
1
Components
Battery
5y 11m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
Projected COD moved
4 times
May 2023 → Jun 2028
Net change
+61 months
first report to latest
Capacity
201 → 201 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
- 2025-02·Balanced Rock Power (BRP)→GridStorenergy-storage.news
Milestones in this assessment
GridStor acquires 150MW/300MWh Texas BESS from BRP (may be this project or related asset)
energy-storage.newsRevised proposed COD per Jan 2025 queue update
interconnectionfyi.substack.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- energy-storage.news/gridstor-acquires-150mw-300mwh-texas-bess-from-brp/
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-7d3
- zonebourse.com/cours/action/ENGIE-4995/actualite/ENGIE-Liste-des-filiales-et-participations-2024-49180170/
- zonebourse.com/actualite-bourse/engie-liste-des-filiales-et-participations-2025-ce7e5cd8da88ff2d
Commercial operation date: LBNL queue shows June 2028 COD. Interconnection.fyi weekly update (Jan 2025) notes COD was pushed from Nov 2026 to current 2028 target, indicating recent schedule slip. No newer developer announcement contradicts this.
Developer: LBNL filing entity is 'BRP Elbus BESS LLC' (Balanced Rock Power shell). However, Energy-Storage.News (Feb 4, 2025) reports GridStor acquired a 150MW/300MWh Texas BESS from BRP. Project specs differ slightly (150MW vs 201MW), but Zonebourse ENGIE subsidiary lists (2024-2025) show BRP Elbus BESS LLC as 100% ENGIE-owned, suggesting BRP (parent: ENGIE) developed it and GridStor may have acquired a different or related asset. Consensus: currently BRP/ENGIE-owned pending clarification of GridStor deal scope.
Status: LBNL status is 'active' with IA status 'Facility Study'. Interconnection.fyi update confirms recent COD revision, indicating project remains in queue but facing timeline adjustments.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Elbus BESS project is a proposed 200.99 MW battery storage project located in Caldwell County, Texas. Developed by BRP Elbus BESS LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0135, with a queue entry date of December 3, 2020.
The proposed commercial operation date for the Elbus BESS project is June 1, 2028. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is the 9075 Lytton 138kV. The project has appeared in recent news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Caldwell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Elbus BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
9075 Lytton 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Lytton Springs Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.