Cantaloupe Solar
307 MW generation in Reeves, TX · In queue since December 2020 · Proposed COD July 2028
307 MW
Capacity
1
Components
Solar
5y 7m
In Queue
IA Executed
IA Phase
Signed Apr 2024
Queue → IA
3y 4m
IA → COD
4y 3m
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-07-01
ERCOT Standard Generation Interconnection Agreement executed between AEP Texas Inc. and Saragosa Del Sol Energy, LLC
sourceFractal Advisory launches sale process for DC-coupled Solar PV + BESS project in Reeves County
sourceERCOT capacity chart lists 303.13 MW solar project with 2028 target COD
sourceCantaloupe Solar is a proposed 303.13 MW solar generation project located in Reeves County, Texas. The project, developed by Saragosa Del Sol Energy, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-23INR0116, with a queue entry date of December 22, 2020. The proposed commercial operation date is July 1, 2028.
The interconnection agreement for Cantaloupe Solar was executed on April 23, 2024. The point of interconnection is the 60716 Saragosa 138kV substation. The project has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Saragosa Del Sol Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60716 Saragosa 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Saragosa Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.