BRP Rhine BESS
206.89 MW storage in Ward, TX · In queue since August 2020 · Proposed COD December 2028
206.89 MW
Capacity
1
Components
Battery
6y 3m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 4m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Projected COD moved
4 times
Mar 2023 → Dec 2028
Net change
+69 months
first report to latest
Capacity
202 → 207 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Queue application submitted to ERCOT, assigned ID 23INR0075
interconnection.fyiResearch sources and reasoning (3 recorded sources)
medium confidence at research time
- interconnection.fyi/project/ercot-23inr0075
- live.euronext.com/sites/default/files/company_press_releases/attachments/2026/02/26/cpr03_lesechos_16165_1391055_Liste_des_filiales_et_participations_2025.pdf
- zonebourse.com/cours/action/ENGIE-4995/actualite/ENGIE-Liste-des-filiales-et-participations-2024-49180170/
Commercial operation date: LBNL queue snapshot shows proposed COD of December 1, 2028. No independent news sources or press releases found to validate or contradict this date.
Developer: LBNL filing entity is 'BRP Rhine BESS LLC', a project-specific shell. ENGIE's 2024 and 2025 subsidiary disclosure documents (Euronext filings) list 'BRP Rhine BESS LLC' as a 100%-owned subsidiary under full integration, confirming ENGIE as the parent operating company.
Status: LBNL status is 'active' with IA status 'Facility Study'. No news coverage indicates construction start, financing close, or withdrawal. Project remains in early interconnection study phase.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The BRP Rhine BESS project is a proposed 206.89 MW battery storage project located in Ward County, Texas. The developer is BRP Rhine BESS LLC. It is interconnected within the ERCOT region under queue ID ERCOT-23INR0075, with an interconnection queue entry date of August 4, 2020.
The proposed commercial operation date for the BRP Rhine BESS project is December 1, 2028. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 11188 QUARRYFLD - 11010 WOLF.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ward
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Rhine BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 11188 QUARRYFLD - 11010 WOLF
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
BRP Rhine BESS
Data-driven briefing on BRP Rhine BESS — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.