Noria Solar DCC
145 MW generation in Nueces, TX · In queue since August 2020 · Proposed COD April 2028
145 MW
Capacity
1
Components
Solar
6y 3m
In Queue
—
IA Status
Signed Oct 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 2m
IA → COD
5y 6m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2028-04-21
Projected COD moved
5 times
Jun 2023 → Apr 2028
Net change
+58 months
first report to latest
Capacity
145 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection agreement executed with AEP TEXAS INC
eta-publications.lbl.govProposed completion changed from August 31, 2025 to October 12, 2026
interconnectionfyi.substack.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/developers/talen-energy
- interconnectionfyi.substack.com/p/interconnectionfyi-weekly-digest
- eta-publications.lbl.gov/sites/default/files/2024-09/hybrid_plant_tracking_2024_data_workbook.xlsx
- ercot.com/files/docs/2025/02/12/CapacityDemandandReservesReport_December2024.pdf
- assets.comptroller.texas.gov/ch313/1640/1640-riviera-noria-cert.pdf
Commercial operation date: LBNL shows 2027-10-01, but Interconnection.fyi (Dec 2024) reports proposed completion changed to October 12, 2026. ERCOT CDR reports from late 2024/early 2025 show 2025 target, suggesting ongoing delays. Most recent specific date is Oct 2026.
Developer: Cleanview identifies Talen Energy as the developer with Noria Solar DCC in their pipeline. LBNL hybrid tracking data and Texas.gov documents show legal entity as 'Noria Hondo Solar, LLC', a project-specific LLC.
Status: LBNL shows active status with IA executed 2022-10-12. Multiple ERCOT reports (CDR Dec 2024, MORA) confirm project remains in planned status with no withdrawal signals.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Noria Solar DCC project is a proposed 145 MW solar generation project located in Nueces County, Texas. Developed by Noria Hondo Solar, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-23INR0061. The project entered the interconnection queue on August 4, 2020, and has a proposed commercial operation date of October 1, 2027.
The project's Interconnection Agreement (IA) was executed on October 12, 2022. The point of interconnection (POI) is the 85000 Nelson Sharpe 345kV location. The project is currently listed as active in the interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Nueces
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.