Briefing/projectactive
Noria Solar DCC is a 145 MW Solar project in Texas, currently active.
Proposed COD is 2027-10-01.
- Queue ID
- ERCOT-23INR0061
- Location
- Nueces, Texas
- Technology
- Solar
- Market / region
- ERCOT
What stands out
1
Noria Solar DCC is a 145 MW Solar project in Texas with status active.
2
proposed COD is 2027-10-01.
Market and operating context
- Queue date
- 2020-08-03
- Proposed COD
- 2027-10-01
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.