Caliche Mound Solar (ERCOT-23INR0056) — Project Summary

Queue ID
ERCOT-23INR0056
Capacity
406.6 MW
Technology
Solar
Status
active
Location
Deaf Smith, TX
Region
ERCOT
Developer
Tierra Blanco Solar LLC
IA Status
IA Executed

Caliche Mound Solar

ERCOT-23INR0056BetaActiveSolarERCOTLBNL + Live

406.6 MW generation in Deaf Smith, TX · In queue since July 2020 · Proposed COD October 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

406.6 MW

Capacity

1

Components

Solar

6 years

In Queue

IA Executed

IA Phase

Signed Oct 2023

Interconnection

Queue → IA

3y 3m

IA → COD

4 years

Total Duration

3y 3m

Construction75%
Queue EntryJul 24, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 12, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-10-26

Cross-source intelligence
Beta
High confidence·4 sources·as of 2026-06-01
Expected COD
2026
Queue date 1–2 years staleQueue: 2027-10-26
Developer
Intersect Power
Filed as Tierra Blanco Solar LLC
Status
IA Executed
IA Executed — interconnection infrastructure complete as of June 2025, project advancing toward 2026 COD
Financing
Unannounced
Key milestones
IA executedOct 12, 2023

Interconnection agreement executed between Oncor and Caliche Mound Solar LLC, filed with Texas PUC

source
Permit approvedFeb 2024

Deaf Smith County Commission approved Reinvestment Zone and Tax Abatement Agreement for Intersect Power solar expansion

source
GroundbreakingJun 2025

Mule Deer Switch Station construction completed, enabling project interconnection to ERCOT transmission network

source
COD target2026Most recent

ERCOT MORA report lists project with 2026 expected online date

source
About

Caliche Mound Solar is a proposed 408.21 MW solar generation project located in Deaf Smith County, Texas. The project, developed by Tierra Blanco Solar LLC, is in the ERCOT interconnection queue as entry ERCOT-23INR0056, with a queue entry date of July 24, 2020. The proposed commercial operation date is October 15, 2027.

The project's interconnection agreement has been executed as of October 12, 2023. The point of interconnection is at tap 345kV 23906 AJSwope - 23910 Windmill. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Deaf Smith

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Tierra Blanco Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 23906 AJSwope - 23910 Windmill

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.