Caliche Mound Solar
406.6 MW generation in Deaf Smith, TX · In queue since July 2020 · Proposed COD October 2027
406.6 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Executed
IA Phase
Signed Oct 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 3m
IA → COD
4 years
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2027-10-26
Projected COD moved
5 times
May 2023 → Oct 2027
Net change
+53 months
first report to latest
Capacity
406 → 407 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
- 2026-03·Intersect Power→Google (acquired Intersect Power)energy-storage.news
Milestones in this assessment
Interconnection agreement executed with Oncor (signed Oct 2023). The Oncor/Caliche Mound Solar, LLC IA was filed at the Texas PUC on 2023-10-26.
infrasure.aiDeaf Smith County Commission approved a Reinvestment Zone and Tax Abatement Agreement for the Intersect Power solar expansion.
abc7amarillo.comGoogle completed its US$4.75B acquisition of Intersect Power, the developer associated with this project. The project's inclusion in the deal is not explicitly confirmed.
energy-storage.newsResearch sources and reasoning (8 recorded sources)
medium confidence at research time
- abc7amarillo.com/news/local/deaf-smith-county-commission-clears-way-for-hydrogen-plant-wind-farm-solar-farm-intersect-power
- infrasure.ai/project/ercot-23inr0056-caliche-mound-solar
- interconnection.fyi/project/ercot-23inr0056
- ercotqueue.com/project/23INR0056
- app.nrgmap.com/queues/ercot-23inr0056
- interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=1688
- energy-storage.news/google-completes-us4-75-billion-intersect-power-acquisition-initial-focus-on-california-texas-solar-plus-storage/
- cleanview.co/power-projects/planned/solar-farms/texas/23INR0056/caliche-mound-solar-
Commercial operation date: Only the LBNL/ERCOT proposed COD of 2027-10-26 is available. Aggregators (interconnection.fyi, infrasure, cleanview) repeat 'October 2027' / 'expected online 2027' but appear to mirror the queue data, and no developer or press source gives a financing-backed date. FutureGrid's 2025-08-28 in-service date is older and unsupported by any other source.
Developer: Local news on the Deaf Smith County tax abatement ties the project to Intersect Power, while LBNL lists the shell LLC Tierra Blanco Solar LLC. Other trackers name CIG DS1 LLC, and the Oncor IA names Caliche Mound Solar, LLC, which are likely sibling project entities. Google completed its acquisition of Intersect Power in March 2026, but no source explicitly links this project to that deal.
Status: LBNL shows IA Executed and active, and the Oncor IA was filed at the Texas PUC on 2023-10-26. NRG Map confirms the project is still active. interxdata's 'operational' label conflicts with the other sources and the 2027 proposed COD, so I discounted it.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Caliche Mound Solar is a proposed 408.21 MW solar generation project located in Deaf Smith County, Texas. The project, developed by Tierra Blanco Solar LLC, is in the ERCOT interconnection queue as entry ERCOT-23INR0056, with a queue entry date of July 24, 2020. The proposed commercial operation date is October 15, 2027.
The project's interconnection agreement has been executed as of October 12, 2023. The point of interconnection is at tap 345kV 23906 AJSwope - 23910 Windmill. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Deaf Smith
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tierra Blanco Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 23906 AJSwope - 23910 Windmill
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.