Caliche Mound Solar (ERCOT-23INR0056) — Project Summary

Queue ID
ERCOT-23INR0056
Capacity
406.6 MW
Technology
Solar
Status
active
Location
Deaf Smith, TX
Region
ERCOT
Developer
Tierra Blanco Solar LLC
IA Status
IA Executed

Caliche Mound Solar

ERCOT-23INR0056BetaActiveSolarERCOTLBNL + Live

406.6 MW generation in Deaf Smith, TX · In queue since July 2020 · Proposed COD October 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

406.6 MW

Capacity

1

Components

Solar

6y 4m

In Queue

IA Executed

IA Phase

Signed Oct 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 3m

IA → COD

4 years

Total Duration

3y 3m

Construction75%
Queue EntryJul 24, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 12, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-10-26

Queue history
23INR0056 · 75 monthly ERCOT reports, Jul 2020 – Sep 2026

Projected COD moved

5 times

May 2023 → Oct 2027

Net change

+53 months

first report to latest

Capacity

406 → 407 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJul 24, 2020
Facilities study approvedSep 17, 2026
Interconnection agreement signedOct 12, 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Oct 26, 2027
From queue filing
Developer in saved assessment
Intersect Power (Google-owned)
Ownership change in saved research
Status at research time
IA Executed
Active in the ERCOT queue with an IA executed in Oct 2023 (Oncor / Caliche Mound Solar, LLC). The Mule Deer Switch Station is reported complete. No confirmed construction start or COD.
Financing
Not recorded
Ownership history
  1. 2026-03·Intersect Power→Google (acquired Intersect Power)energy-storage.news

Milestones in this assessment

IA executedOct 12, 2023

Interconnection agreement executed with Oncor (signed Oct 2023). The Oncor/Caliche Mound Solar, LLC IA was filed at the Texas PUC on 2023-10-26.

infrasure.ai
Permit approvedFeb 13, 2024

Deaf Smith County Commission approved a Reinvestment Zone and Tax Abatement Agreement for the Intersect Power solar expansion.

abc7amarillo.com
Ownership changeMar 13, 2026Latest in this assessment

Google completed its US$4.75B acquisition of Intersect Power, the developer associated with this project. The project's inclusion in the deal is not explicitly confirmed.

energy-storage.news
Research sources and reasoning (8 recorded sources)

medium confidence at research time

  1. abc7amarillo.com/news/local/deaf-smith-county-commission-clears-way-for-hydrogen-plant-wind-farm-solar-farm-intersect-power
  2. infrasure.ai/project/ercot-23inr0056-caliche-mound-solar
  3. interconnection.fyi/project/ercot-23inr0056
  4. ercotqueue.com/project/23INR0056
  5. app.nrgmap.com/queues/ercot-23inr0056
  6. interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=1688
  7. energy-storage.news/google-completes-us4-75-billion-intersect-power-acquisition-initial-focus-on-california-texas-solar-plus-storage/
  8. cleanview.co/power-projects/planned/solar-farms/texas/23INR0056/caliche-mound-solar-

Commercial operation date: Only the LBNL/ERCOT proposed COD of 2027-10-26 is available. Aggregators (interconnection.fyi, infrasure, cleanview) repeat 'October 2027' / 'expected online 2027' but appear to mirror the queue data, and no developer or press source gives a financing-backed date. FutureGrid's 2025-08-28 in-service date is older and unsupported by any other source.

Developer: Local news on the Deaf Smith County tax abatement ties the project to Intersect Power, while LBNL lists the shell LLC Tierra Blanco Solar LLC. Other trackers name CIG DS1 LLC, and the Oncor IA names Caliche Mound Solar, LLC, which are likely sibling project entities. Google completed its acquisition of Intersect Power in March 2026, but no source explicitly links this project to that deal.

Status: LBNL shows IA Executed and active, and the Oncor IA was filed at the Texas PUC on 2023-10-26. NRG Map confirms the project is still active. interxdata's 'operational' label conflicts with the other sources and the 2027 proposed COD, so I discounted it.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Caliche Mound Solar is a proposed 408.21 MW solar generation project located in Deaf Smith County, Texas. The project, developed by Tierra Blanco Solar LLC, is in the ERCOT interconnection queue as entry ERCOT-23INR0056, with a queue entry date of July 24, 2020. The proposed commercial operation date is October 15, 2027.

The project's interconnection agreement has been executed as of October 12, 2023. The point of interconnection is at tap 345kV 23906 AJSwope - 23910 Windmill. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Deaf Smith

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Tierra Blanco Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV 23906 AJSwope - 23910 Windmill

Data Source

LBNL + Live

DeveloperIntersect PowerKVII · 2024-02-13
TransactionTax equityKVII · 2024-02-13
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.