Tanglewood Solar (ERCOT-23INR0054) — Project Summary

Queue ID
ERCOT-23INR0054
Capacity
250.96 MW
Technology
Solar
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
Brazoria Solar, LLC
IA Status
IA Executed

Tanglewood Solar

ERCOT-23INR0054BetaActiveSolarERCOTLBNL + Live

250.96 MW generation in Brazoria, TX · In queue since July 2020 · Proposed COD September 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

250.96 MW

Capacity

1

Components

Solar

6y 4m

In Queue

IA Executed

IA Phase

Signed Nov 2022

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 4m

IA → COD

3y 10m

Total Duration

2y 4m

Schedule

2 months past proposed COD

Construction75%
Queue EntryJul 10, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 1, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-09-30

Queue history
23INR0054 · 69 monthly ERCOT reports, Jan 2021 – Sep 2026

Projected COD moved

10 times

Oct 2023 → Sep 2026

Net change

+35 months

first report to latest

Capacity

400 → 251 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJul 10, 2020
Facilities study approvedJun 3, 2024
Interconnection agreement signedNov 1, 2022
Approved for energizationAug 5, 2025
Approved for synchronizationAug 20, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 5y 9m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneEPC contract awardedPV Tech · 2021-02-13

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Apr 30, 2026
Differs from queue: Sep 30, 2026From queue filing
Developer in saved assessment
Brazoria Solar, LLC
Filed as Brazoria Solar I, LLC
Status at research time
Active
Active — IA executed November 2022, interconnection filings ongoing with CenterPoint as of April-May 2025
Financing
Not recorded

Milestones in this assessment

IA executedNov 1, 2022

Interconnection Agreement executed with ERCOT

interconnection.fyi
COD targetApr 2026Latest in this assessment

Expected online April 2026 per queue filing

cleanview.co
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. interconnection.fyi/project/ercot-23inr0054
  2. cleanview.co/power-projects/planned/solar-farms/texas/23INR0054/tanglewood-solar
  3. interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&ItemMatch=Equal&FilingParty=centerpoint&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
  4. assets.comptroller.texas.gov/ch313/1803/1803-angleton-brazoria-appamend1.pdf
  5. ercotqueue.com/project/23INR0054

Commercial operation date: LBNL queue snapshot shows proposed COD of 2026-04-30. Multiple aggregator sites (Cleanview, ercotqueue.com) echo this April 2026 date. No independent press releases or developer announcements found to validate or contradict.

Developer: LBNL filing entity is 'Brazoria Solar, LLC'. Texas Comptroller document (July 2022) reveals the legal entity is 'Brazoria Solar I, LLC' and notes the project is referred to as 'Tanglewood Solar' in ERCOT interconnect process. No parent operating company identified in search results.

Status: LBNL shows 'active' status with IA executed 2022-11-01. Texas PUC Interchange shows recent filings (April 2025) for interconnection agreements with CenterPoint Energy, confirming active development.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Tanglewood Solar is a proposed 250.96 MW solar generation project located in Brazoria County, Texas. The project, developed by Brazoria Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-23INR0054, with a queue entry date of July 10, 2020. The proposed commercial operation date is March 15, 2026.

The project's interconnection agreement (IA) has been executed as of November 1, 2022. The point of interconnection (POI) is the 345kV Seabreeze Substation. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Brazoria

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Brazoria Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

345kV Seabreeze Substation

Data Source

LBNL + Live

DeveloperOrigis EnergyPV Tech · 2021-02-13
EPC contractorRenewable Energy SystemsPV Tech · 2021-02-13
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.