Camino Santiago Solar (ERCOT-22INR0605) — Project Summary

Queue ID
ERCOT-22INR0605
Capacity
196.3 MW
Technology
Solar
Status
active
Location
Milam, TX
Region
ERCOT
Developer
Camino Solar Project, LLC
IA Status
IA Executed

Camino Santiago Solar

ERCOT-22INR0605BetaActiveSolarERCOTLBNL + Live

196.3 MW generation in Milam, TX · In queue since September 2022 · Proposed COD September 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

196.3 MW

Capacity

1

Components

Solar

4y 2m

In Queue

IA Executed

IA Phase

Signed Dec 2024

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 3m

IA → COD

2y 9m

Total Duration

2y 3m

Construction75%
Queue EntrySep 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 6, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-09-01

Queue history
22INR0605 · 44 monthly ERCOT reports, Feb 2023 – Sep 2026

Projected COD moved

4 times

Jul 2025 → Sep 2027

Net change

+26 months

first report to latest

Capacity

181 → 196 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedSep 2, 2022
Facilities study approvedSep 17, 2026
Interconnection agreement signedDec 6, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Feb 18, 2027
Differs from queue: Sep 1, 2027From queue filing
Developer in saved assessment
Ferrovial
Filed as Camino Solar Project, LLC
Status at research time
IA Executed
IA Executed (Dec 2024) — Ferrovial announced development in Aug 2025, construction phase imminent for 2027 COD
Financing
Not recorded

Milestones in this assessment

IA executedDec 6, 2024

Interconnection Agreement executed with ERCOT

interconnectionfyi.substack.com
Ownership changeAug 2025

Ferrovial announces development of 250 MW solar facility in Milam County

newsroom.ferrovial.com
COD targetFeb 18, 2027Latest in this assessment

Target commercial operation date per ERCOT capacity planning

ercot.com
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. newsroom.ferrovial.com/en-us/press-releases/ferrovial-to-develop-250-mw-solar-facility-in-milam-county-texas/
  2. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-7d3
  3. ercot.com/files/docs/2025/12/04/Capacity-Changes-by-Fuel-Type-Charts_November_2025_PlannedMonthly.xlsx
  4. cleanview.co/power-projects/planned/solar-farms/texas/22INR0605/camino-santiago-solar

Commercial operation date: LBNL proposed COD of Feb 2027 is corroborated by ERCOT's December 2025 capacity planning chart showing 2027 online date. Ferrovial press release (Aug 2025) announces development but doesn't contradict this timeline.

Developer: LBNL filing uses project-LLC 'Camino Solar Project, LLC'. Ferrovial's August 2025 press release announces they will develop, construct, operate and maintain this 250 MW solar facility in Milam County, TX — matching location and scale, indicating Ferrovial is the operating parent company.

Status: LBNL shows IA executed December 6, 2024. Ferrovial's August 2025 announcement confirms active development with construction, operation and maintenance responsibilities assigned.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Camino Santiago Solar project is a proposed 196.3 MW solar generation project located in Milam County, Texas. The developer is Camino Solar Project, LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0605, with a queue entry date of September 2, 2022, and a proposed commercial operation date of February 18, 2027.

The project's Interconnection Agreement (IA) has been executed as of December 6, 2024. The point of interconnection (POI) is at Tap 345kV 3687 Bell County East Switch _x0013_ 39950 TNP One Plant Ckt 2 (North Circuit). The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Milam

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Camino Solar Project, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 3687 Bell County East Switch – 39950 TNP One Plant Ckt 2 (North Circuit).

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.