Roseland Solar II (ERCOT-22INR0506) — Project Summary

Queue ID
ERCOT-22INR0506
Capacity
254 MW
Technology
Solar
Status
active
Location
Falls, TX
Region
ERCOT
Developer
Enel Green Power Roseland Solar, LLC
IA Status
IA Executed

Roseland Solar II

ERCOT-22INR0506BetaActiveSolarERCOTLBNL + Live

254 MW generation in Falls, TX · In queue since October 2021 · Proposed COD October 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

254 MW

Capacity

1

Components

Solar

5y 1m

In Queue

IA Executed

IA Phase

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5 years

Schedule

2 months past proposed COD

Construction75%
Queue EntryOct 5, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-10-05

Queue history
22INR0506 · 60 monthly ERCOT reports, Oct 2021 – Sep 2026

Projected COD moved

21 times

Jul 2022 → Oct 2026

Net change

+51 months

first report to latest

Capacity

254 MW

unchanged in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 5, 2021
Facilities study approvedOct 25, 2021
Interconnection agreement signedDec 10, 2020
Approved for energizationJun 7, 2022
Approved for synchronizationSep 26, 2022

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2024
Differs from queue: Oct 5, 2026
Developer in saved assessment
Enel Green Power North America
Filed as Enel Green Power Roseland Solar, LLC
Status at research time
Online
Online — operational as of 2024-2025, hosting community programs including beekeeping therapy partnerships
Financing
Secured
Construction financing secured by May 2021 as part of Enel's 1.5 GW portfolio announcement; project completed and operational

Milestones in this assessment

IA executed2021

IA executed as part of ERCOT queue process, construction announced May 2021

enelgreenpower.com
GroundbreakingMay 2021

Construction started on Roseland Solar II as part of 1.5 GW portfolio including 319 MW storage

enelgreenpower.com
Financing closeMay 2021

Financing secured for construction start on five renewable projects totaling 1.5 GW

enelgreenpower.com
COD target2024Latest in this assessment

Project operational by August 2025 per FOX 44 coverage of active facility

fox44news.com
Research sources and reasoning (3 recorded sources)

high confidence at research time

  1. fox44news.com/news/local-news/falls-county/central-texas-solar-farm-produces-more-than-energy/
  2. kwtx.com/2026/03/30/nonprofit-partners-with-solar-farms-provide-beekeeping-therapy-veterans-first-responders/
  3. enelgreenpower.com/media/press/2021/05/enel-green-power-north-america-announces-construction-1-5-gw-new-renewables-plus-319-mw-storage-capacity-us

Commercial operation date: FOX 44 article from August 2025 describes Roseland Solar Farm as operational ('produces more than energy'), and KWTX March 2026 article confirms ongoing operations with beekeeping programs. LBNL's November 2025 target appears to have been met or slightly advanced, suggesting 2024 completion.

Developer: LBNL filing uses project-specific LLC 'Enel Green Power Roseland Solar, LLC' while operational references (FOX 44, KWTX) cite 'Enel North America' and Enel's May 2021 press release announces construction under 'Enel Green Power North America' as the operating parent company.

Status: Multiple 2025-2026 news articles describe the facility as operational ('produces more than energy', active beekeeping programs). LBNL status shows 'active' with IA executed, but ground reality confirms commercial operation achieved.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Roseland Solar II is a proposed 254 MW solar generation project located in Falls County, Texas. The developer is Enel Green Power Roseland Solar, LLC. The project is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-22INR0506 on October 5, 2021. The proposed commercial operation date is November 29, 2025, and the Interconnection Agreement has been executed as of December 10, 2020.

The point of interconnection is at tap 345kV 3390 Jewett - 3399 Ratsnake. The project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Falls

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Enel Green Power Roseland Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV 3390 Jewett - 3399 Ratsnake

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Jewett Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-14

View all articles