Roseland Solar II
254 MW generation in Falls, TX · In queue since October 2021 · Proposed COD October 2026
254 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5 years
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2026-10-05
Projected COD moved
21 times
Jul 2022 → Oct 2026
Net change
+51 months
first report to latest
Capacity
254 MW
unchanged in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
IA executed as part of ERCOT queue process, construction announced May 2021
enelgreenpower.comConstruction started on Roseland Solar II as part of 1.5 GW portfolio including 319 MW storage
enelgreenpower.comFinancing secured for construction start on five renewable projects totaling 1.5 GW
enelgreenpower.comProject operational by August 2025 per FOX 44 coverage of active facility
fox44news.comResearch sources and reasoning (3 recorded sources)
high confidence at research time
- fox44news.com/news/local-news/falls-county/central-texas-solar-farm-produces-more-than-energy/
- kwtx.com/2026/03/30/nonprofit-partners-with-solar-farms-provide-beekeeping-therapy-veterans-first-responders/
- enelgreenpower.com/media/press/2021/05/enel-green-power-north-america-announces-construction-1-5-gw-new-renewables-plus-319-mw-storage-capacity-us
Commercial operation date: FOX 44 article from August 2025 describes Roseland Solar Farm as operational ('produces more than energy'), and KWTX March 2026 article confirms ongoing operations with beekeeping programs. LBNL's November 2025 target appears to have been met or slightly advanced, suggesting 2024 completion.
Developer: LBNL filing uses project-specific LLC 'Enel Green Power Roseland Solar, LLC' while operational references (FOX 44, KWTX) cite 'Enel North America' and Enel's May 2021 press release announces construction under 'Enel Green Power North America' as the operating parent company.
Status: Multiple 2025-2026 news articles describe the facility as operational ('produces more than energy', active beekeeping programs). LBNL status shows 'active' with IA executed, but ground reality confirms commercial operation achieved.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Roseland Solar II is a proposed 254 MW solar generation project located in Falls County, Texas. The developer is Enel Green Power Roseland Solar, LLC. The project is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-22INR0506 on October 5, 2021. The proposed commercial operation date is November 29, 2025, and the Interconnection Agreement has been executed as of December 10, 2020.
The point of interconnection is at tap 345kV 3390 Jewett - 3399 Ratsnake. The project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Falls
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Enel Green Power Roseland Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 3390 Jewett - 3399 Ratsnake
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Jewett Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesHecate Grid Gwent Storage 1
Data-driven briefing on Hecate Energy — fleet, generation, financial, and news signals.
Roseland Solar II
Data-driven briefing on Roseland Solar II — fleet, generation, financial, and news signals.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Hecate Energy Ramsey Storage
Data-driven briefing on Hecate Energy — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.