Venture Hill Storage (ERCOT-22INR0488) — Project Summary

Queue ID
ERCOT-22INR0488
Capacity
70.44 MW
Technology
Battery
Status
active
Location
Travis, TX
Region
ERCOT
Developer
KCE TX 24, LLC
IA Status
Facility Study

Venture Hill Storage

ERCOT-22INR0488BetaActiveBatteryERCOTLBNL + Live

70.44 MW storage in Travis, TX · In queue since February 2021 · Proposed COD December 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

70.44 MW

Capacity

1

Components

Battery

5y 9m

In Queue

Facility Study

IA Phase

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 10m

Facilities Study50%
Queue EntryFeb 9, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Queue history
22INR0488 · 69 monthly ERCOT reports, Jan 2021 – Sep 2026

Projected COD moved

4 times

Dec 2022 → Dec 2026

Net change

+48 months

first report to latest

Capacity

58 → 70 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 9, 2021

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 2y 10m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneunder constructionUtility Dive · 2024-01-22
Expected COD2024-07Utility Dive · 2024-01-22
Project lifecycle
as of 2024-01-22
PhaseConstructionUtility Dive · 2024-01-22
OperationalNoUtility Dive · 2024-01-22
TechnologyBatteryUtility Dive · 2024-01-22
DeveloperApex Clean EnergyUtility Dive · 2024-01-22

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Venture Hill Storage project is a proposed 70.44 MW battery storage project located in Travis County, Texas. Developed by KCE TX 24, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0488, with a queue entry date of February 9, 2021. The proposed commercial operation date is December 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.

The Venture Hill Storage project has been the subject of recent news coverage, with seven articles published related to the project. These articles primarily focus on deals, regulatory matters, and industry news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Travis

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

KCE TX 24, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

7336 Gilleland Creek 138kV

Data Source

LBNL + Live

DeveloperApex Clean EnergyUtility Dive · 2024-01-22
TransactionAcquisitionTotalEnergies.com · 2024-12-04
OfftakerTotalEnergiesTotalEnergies.com · 2024-12-04
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
SLCN_ESS_ALL
POI Substation
Gilleland Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.