Pachanga Wind
300 MW generation in Cameron, TX · In queue since February 2021 · Proposed COD April 2030
300 MW
Capacity
1
Components
Wind
5y 9m
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9y 2m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-04-08
Projected COD moved
4 times
Jul 2023 → Apr 2030
Net change
+81 months
first report to latest
Capacity
300 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-22inr0480-pachanga-wind
- ercotqueue.com/project/22INR0480
- interconnection.fyi/project/ercot-22inr0480
- cleanview.co/power-projects/planned/wind-farms/texas/22INR0480/pachanga-wind-
- bizapedia.com/tx/pachanga-wind-llc.html
Commercial operation date: Only the LBNL/ERCOT proposed COD of 2030-04-08 exists; aggregator sites (cleanview, infrasure) repeat it from the same queue data and add no independent developer-backed target. No press releases or news give a different date.
Developer: Only the project LLC is identified. Corporate registry results show a Texas LLC formed 2021-02-01 with an Austin registered address, but no parent or operating company is named in any source.
Status: LBNL and queue trackers (interconnection.fyi, ercotqueue.com) agree the project is active with no IA. The interxdata 'operational' label conflicts with all other sources and is likely a data error. ercotqueue.com lists a 19% build-chance.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Pachanga Wind is a proposed 300 MW wind generation project located in Cameron County, Texas. The project, developed by Pachanga Wind LLC, is currently in the ERCOT interconnection queue as entry ERCOT-22INR0480, with a queue entry date of February 9, 2021. Its proposed commercial operation date is April 8, 2030, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 300 MW of wind generation capacity. It is planned to interconnect at the tap 345kV 5966 Palmito - 80137 Stewart Rd point of interconnection. The Pachanga Wind project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pachanga Wind LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 5966 Palmito - 80137 Stewart Rd
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Palmito Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Max 4 Wind
Data tables and metrics from the InfraSure database.
FPL Energy Oliver Wind II LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.