BRP Kabru BESS
202.45 MW storage in Andrews, TX · In queue since October 2020 · Proposed COD December 2028
202.45 MW
Capacity
1
Components
Battery
5y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
8y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The BRP Kabru BESS project is a proposed 202.45 MW battery storage project located in Andrews County, Texas. The developer is BRP Kabru BESS LLC. This project is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0427, with a queue entry date of October 7, 2020.
The proposed commercial operation date for the project is December 1, 2028. Its interconnection status is currently in the Facility Study phase. Recent news coverage has discussed this project.
Generated from interconnection queue and public data sources
State
TX
County
Andrews
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP Kabru BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1159 Andrew North - 11284 Blackbird 138kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about BRP Kabru BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.