Briefing on BRP Kabru BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
202 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-12-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

BRP Kabru BESS is a 202 MW Battery project in Texas, currently active.

BRP Kabru BESS LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-12-01.

Queue ID
ERCOT-22INR0427
Location
Andrews, Texas
Technology
Battery
Developer
BRP Kabru BESS LLC
Market / region
ERCOT
Point of interconnection
1159 Andrew North - 11284 Blackbird 138kV

What stands out

1

BRP Kabru BESS is a 202 MW Battery project in Texas with status active.

2

BRP Kabru BESS LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-12-01.

Market and operating context

Queue date
2020-10-07
Proposed COD
2028-12-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

BRP Kabru BESS — verified asset snapshot

FieldValue
Queue IDERCOT-22INR0427
LocationAndrews, Texas
TechnologyBattery
DeveloperBRP Kabru BESS LLC
Market / regionERCOT
Point of interconnection1159 Andrew North - 11284 Blackbird 138kV
Queue date2020-10-07
Proposed COD2028-12-01