BRP Octans BESS
129.57 MW storage in Pecos, TX · In queue since July 2020 · Proposed COD December 2029
129.57 MW
Capacity
1
Components
Battery
6y 4m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9y 5m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
Projected COD moved
4 times
Nov 2022 → Dec 2029
Net change
+85 months
first report to latest
Capacity
127 → 130 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue at Facility Study stage
interconnection.fyiResearch sources and reasoning (3 recorded sources)
medium confidence at research time
- interconnection.fyi/project/ercot-22inr0386
- live.euronext.com/sites/default/files/company_press_releases/attachments/2026/02/26/cpr03_lesechos_16165_1391055_Liste_des_filiales_et_participations_2025.pdf
- zonebourse.com/actualite-bourse/engie-liste-des-filiales-et-participations-2025-ce7e5cd8da88ff2d
Commercial operation date: Only LBNL queue data provides a COD of December 2029. No news or press releases found to validate or contradict this date.
Developer: LBNL filing entity is 'BRP OCTANS BESS LLC', a project SPV. ENGIE's 2024-2025 subsidiary disclosure lists 'BRP Octans BESS LLC' as a 100% owned subsidiary under integration, confirming ENGIE as the parent operating company.
Status: LBNL shows 'Active' status at Facility Study stage. No news coverage found indicating construction start, financing, or status changes.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The BRP Octans BESS project is a proposed 129.57 MW battery storage project located in Pecos County, Texas. The developer is BRP OCTANS BESS LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0386, with an interconnection queue entry date of July 24, 2020. The proposed commercial operation date is December 1, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.
The project is linked to the existing Octans operating plant (EIA ID 65590). The point of interconnection is the 6671 Tombstone 138kV line. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BRP OCTANS BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6671 Tombstone 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- POI Substation
- Tombstone Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.