BRP Musca BESS (ERCOT-22INR0383) — Project Summary

Queue ID
ERCOT-22INR0383
Capacity
100.51 MW
Technology
Battery
Status
active
Location
Reagan, TX
Region
ERCOT
Developer
BRP Musca BESS LLC
IA Status
Facility Study

BRP Musca BESS

ERCOT-22INR0383BetaActiveBatteryERCOTLBNL + Live

100.51 MW storage in Reagan, TX · In queue since July 2020 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

100.51 MW

Capacity

1

Components

Battery

6y 4m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

7y 5m

Facilities Study50%
Queue EntryJul 24, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Queue history
22INR0383 · 74 monthly ERCOT reports, Aug 2020 – Sep 2026

Projected COD moved

3 times

Nov 2022 → Dec 2027

Net change

+61 months

first report to latest

Capacity

101 → 101 MW

changed in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJul 24, 2020
Facilities study approvedDec 8, 2021

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2027
From queue filing
Developer in saved assessment
GridStor
Ownership change in saved research
Status at research time
Active
Active — under construction as of Feb 2025 following GridStor acquisition
Financing
Not recorded
Ownership history
  1. 2025-02·Balanced Rock Power (ENGIE subsidiary)→GridStorenergy-storage.news

Milestones in this assessment

GroundbreakingFeb 2025

Project under construction at time of acquisition announcement

energy-storage.news
Ownership changeFeb 4, 2025Latest in this assessment

GridStor acquired 150MW/300MWh BESS project from Balanced Rock Power

energy-storage.news
Research sources and reasoning (3 recorded sources)

high confidence at research time

  1. energy-storage.news/gridstor-acquires-150mw-300mwh-texas-bess-from-brp/
  2. live.euronext.com/sites/default/files/company_press_releases/attachments/2025/02/27/cpr03_lesechos_16165_1317501_Liste_des_filiales_et_participations_2024.pdf
  3. live.euronext.com/sites/default/files/company_press_releases/attachments/2026/02/26/cpr03_lesechos_16165_1391055_Liste_des_filiales_et_participations_2025.pdf

Commercial operation date: LBNL proposes 2027-12-01 COD. News article from Feb 2025 states project is 'under construction' but provides no updated COD target. No other sources contradict the 2027 timeline.

Developer: LBNL filing entity is 'BRP Musca BESS LLC' (Balanced Rock Power shell). News confirms GridStor acquired the project from Balanced Rock Power in Feb 2025. ENGIE subsidiary filings (Feb 2025, Feb 2026) list BRP Musca BESS LLC as 100% owned, suggesting ENGIE is BRP's parent, but GridStor is now the current owner post-acquisition.

Status: LBNL status is 'Active' at Facility Study stage. News extraction confirms project entered construction phase by Feb 2025 under new owner GridStor.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The BRP Musca BESS project is a proposed 100.51 MW battery storage project located in Reagan County, Texas. The developer is BRP Musca BESS LLC. It is interconnected within the ERCOT region under queue ID ERCOT-22INR0383, with an interconnection queue entry date of July 24, 2020. The project's proposed commercial operation date is December 1, 2027, and its interconnection agreement status is currently in the Facility Study phase.

The proposed project consists of 100.51 MW of battery storage capacity. The BRP Musca BESS project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Reagan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BRP Musca BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

60361 Santa Rita 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Santa Rita Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.