BRP Musca BESS is a 101 MW Battery project in Texas, currently active.
BRP Musca BESS LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-12-01.
- Queue ID
- ERCOT-22INR0383
- Location
- Reagan, Texas
- Technology
- Battery
- Developer
- BRP Musca BESS LLC
- Market / region
- ERCOT
- Point of interconnection
- 60361 Santa Rita 138kV
What stands out
BRP Musca BESS is a 101 MW Battery project in Texas with status active.
BRP Musca BESS LLC is the reported developer.
The reported queue phase is Facility Study; proposed COD is 2027-12-01.
Latest linked story: “GridStor Announces Acquisition of Texas Battery Energy Storage Project From Balanced Rock Power” (Business Wire, 2025-02-03).
Market and operating context
- Queue date
- 2020-07-24
- Proposed COD
- 2027-12-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.