Loma Pinta Solar
203.06 MW generation in La Salle, TX · In queue since June 2020 · Proposed COD May 2028
203.06 MW
Capacity
1
Components
Solar
6y 5m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-31
Projected COD moved
7 times
Dec 2022 → May 2028
Net change
+65 months
first report to latest
Capacity
203 MW
unchanged in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Currently in Facility Study stage, IA not yet executed
interconnection.fyiResearch sources and reasoning (4 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-22inr0357
- cleanview.co/power-projects/planned/solar-farms/texas/22INR0357/loma-pinta-solar
- cleanview.co/power-projects/developers/bordas
- renewablesinfo.org/project/ercot-22inr0357-loma-pinta-solar
Commercial operation date: LBNL queue snapshot shows proposed COD of May 31, 2028. No independent news sources or press releases found to confirm or contradict this date. All search results merely echo the LBNL queue data.
Developer: LBNL filing entity is 'Loma Pinta Wind Energy, LLC' (project-specific shell). Cleanview search result lists this project under 'Bordas's Projects and Development Pipeline', indicating Bordas is the operating parent company behind the shell LLC.
Status: LBNL status is 'active' at Facility Study stage. No news coverage found indicating construction start, financing, or withdrawal. Status appears current.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Loma Pinta Solar project is a proposed 203.06 MW solar generation facility in La Salle County, Texas. The project, developed by Loma Pinta Wind Energy, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0357, with a queue entry date of June 3, 2020. The proposed commercial operation date is May 31, 2028, and the project's interconnection agreement status is Facility Study.
The point of interconnection for the project is the 5705 Fowlerton 138kV location. The Loma Pinta Solar project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
La Salle
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Loma Pinta Wind Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5705 Fowlerton 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Fowlerton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Loma Pinta Solar
Data-driven briefing on Loma Pinta Solar — fleet, generation, financial, and news signals.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.