Skylab Solar
609.74 MW generation in Wharton, TX · In queue since June 2020 · Proposed COD December 2025
609.74 MW
Capacity
1
Components
Solar
6y 5m
In Queue
Facility Study
IA Phase
COD target: 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 6m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
Projected COD moved
2 times
May 2022 → Dec 2025
Net change
+43 months
first report to latest
Capacity
610 MW
unchanged in the reports
Latest stage
Cancelled
last listed Jul 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-22inr0337
- cleanview.co/power-projects/planned/solar-farms/texas/22INR0337/skylab-solar
- infrasure.ai/project/ercot-22inr0337-skylab-solar
Commercial operation date: Only the LBNL date (2025-12-01) is available. Cleanview ('Expected online 2025') and interconnection.fyi ('November 30, 2025') appear to mirror queue data rather than give a developer-backed target. The Skylab hits from NASA and Space.com are unrelated, and the PV Tech 'SkyLab' item is an Australian project.
Developer: Only the queue filing and aggregators derived from it name EDF Renewables Development, Inc. No press release or news confirms a parent, an ownership change, or a different operating company.
Status: interconnection.fyi explicitly says 'The project is currently withdrawn in the ERCOT interconnection queue', which is more recent than the LBNL snapshot. It is a single aggregator source that probably derives from the same queue data, so this is low confidence and should be checked against ERCOT's current queue report. I did not count it as a COD or developer correction, so lbnl_was_stale stays false.
About
Generated Apr 10, 2026 · Predates Jul 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Skylab Solar project is a proposed 609.74 MW solar generation project located in Wharton County, Texas. The project is being developed by EDF Renewables Development, Inc. It is currently active in the ERCOT interconnection queue as entry ERCOT-22INR0337, with a queue entry date of June 3, 2020. The proposed commercial operation date is December 1, 2025.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is tap 345kV 5915 STP - 8249 Angstrom. The Skylab Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jul 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
EDF Renewables Development, Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 5915 STP - 8249 Angstrom
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.