Crowded Star Solar II (ERCOT-22INR0274) — Project Summary

Queue ID
ERCOT-22INR0274
Capacity
189.5 MW
Technology
Solar+Battery
Status
active
Location
Jones, TX
Region
ERCOT
Developer
Jones City Solar II, LLC
IA Status
IA Executed

Crowded Star Solar II

ERCOT-22INR0274BetaActiveSolarBatteryERCOTLBNL + Live

189.5 MW hybrid in Jones, TX · In queue since March 2020 · Proposed COD September 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

189.5 MW

Capacity

1

Components

Solar

6y 8m

In Queue

IA Executed

IA Phase

Signed Jul 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 4m

IA → COD

3y 2m

Total Duration

3y 4m

Schedule

2 months past proposed COD

Construction75%
Queue EntryMar 26, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJul 27, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Completed, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-09-18

Queue history
22INR0274 · 66 monthly ERCOT reports, Mar 2021 – Sep 2026

Projected COD moved

11 times

Jun 2023 → Sep 2026

Net change

+39 months

first report to latest

Capacity

185 → 190 MW

changed in the reports

Latest stage

Synchronized

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 26, 2020
Facilities study approvedNov 5, 2024
Interconnection agreement signedDec 17, 2019
Approved for energizationJun 22, 2026
Approved for synchronizationJul 8, 2026
On ERCOT's inactive listAug 2021 – Aug 2021

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Aug 21, 2026
Differs from queue: Sep 18, 2026From queue filing
Developer in saved assessment
Lightsource bp
Filed as Jones City Solar II, LLC
Status at research time
Active
Active — IA executed July 2023, construction phase underway per BP's Texas solar portfolio activity
Financing
Not recorded

Milestones in this assessment

IA executedJul 27, 2023

Interconnection Agreement executed with ERCOT

ercot.com
COD targetAug 21, 2026Latest in this assessment

Target commercial operation date per ERCOT capacity planning

ercot.com
Research sources and reasoning (4 recorded sources)

medium confidence at research time

  1. industrialinfo.com/iirenergy/industry-news/article/bp-begins-construction-on-texas-solar-farm--324113
  2. cleanview.co/power-projects/developers/lightsource-bp
  3. ercot.com/files/docs/2024/03/06/Capacity_Changes_by_Fuel_Type_Charts_February_2024.xlsx
  4. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending

Commercial operation date: LBNL proposed COD of 2026-08-21 is consistent with ERCOT's February 2024 capacity chart showing 2026 target. No contradictory recent sources found.

Developer: Cleanview pipeline listing explicitly attributes this project to Lightsource bp, while LBNL filing uses project-LLC 'Jones City Solar II, LLC'. Industrial Info Resources article (Dec 2025) confirms BP construction activity in Texas solar.

Status: LBNL shows IA executed 2023-07-27 with active status. Industrial Info Resources (Dec 2025) reports BP construction activity on Texas solar farms, consistent with this project's timeline.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Crowded Star Solar II is a proposed 190.18 MW solar generation project located in Jones County, Texas. The project, developed by Jones City Solar II, LLC, is interconnected within the ERCOT region under queue ID ERCOT-22INR0274. The project consists of 190.18 MW of solar capacity.

The project entered the ERCOT interconnection queue on March 26, 2020, with a proposed commercial operation date of May 29, 2026. The Interconnection Agreement (IA) has been executed as of December 17, 2019. Recent news coverage has discussed the project.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Jones

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Jones City Solar II, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV 68001 Claytonville – 68004 Phantom Hill c2 (New Substation: Open Sky 68014)

Data Source

LBNL + Live

EPC contractorRosendinDallas News · 2025-05-01
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-19

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.